The name of the Procore tool in your environment depends on the language and point-of-view dictionary configured in Procore. See What tool names and terms are different in Procore for main contractors, owners and speciality contractors?
The Procore Standard Budget View is designed for project teams who use Procore's Project Financials tools for budget and contract management. Although most Procore clients enable all of the Project Financials tools, some clients may decide to only use the Budget and Commitments tool in their environment. This means that the Client Contracts, Funding or Main Contracts tool is disabled at the company level. Typically, this decision is made prior to the Procore implementation process.
If the Client Contracts, Funding or Main Contracts tool is disabled in your company's Procore account, your Procore Administrator can follow the steps below to verify that your contract or funding tool is disabled. After verifying the status, your Procore Administrator will need to make a few modifications to the contract-related columns in your company's budget views. This ensures that the calculations designed for use with client contracts, fundings and main contracts are not active in your company's budget views.
To verify that the Client Contracts, Funding or Main Contracts tool is disabled at the Company level:
When the Client Contracts, Funding or Main Contracts tool is disabled at the Company level, follow these steps to modify the columns in the Procore Standard Budget View:
To modify the calculated column named 'Revised Budget' by removing 'Approved COs' from the calculation.
Steps from the Configure Columns window… | Settings |
---|---|
|
To modify the automatic calculation in the standard column named 'Forecast to Complete.'
Steps from the Configure Columns window… | Settings |
---|---|
|
To modify the automatic calculation in the calculated column named 'Projected over Under.'
Steps from the Configure Columns window… | Settings |
---|---|
|
To hide the recommended columns when the Client Contracts, Funding or Main Contracts tool is disabled.
Steps from the Configure Columns window… | Settings |
---|---|
|