Integration by Procore: How do I export cost forecast data from a Procore budget to Viewpoint® Spectrum®?

Answer

For companies that have integrated Procore with Viewpoint® Spectrum®, you can import your real-time actual cost data from Viewpoint® Spectrum® into Procore's Budget tool. This lets project teams leverage their Viewpoint® Spectrum® cost data with the 'Estimated Cost' value in a Procore budget to calculate the budget's 'Estimated Cost at Completion' value. This export capability provides your project's accounting team with the complimentary benefit of being able to access Procore's 'Estimated Cost at Completion' values in Viewpoint® Spectrum®.

To turn on forecasting/projections: 

  1. Navigate to the project Budget tool
  2. Click on the settings icon-settings-gear-android.png icon.
  3. Change the following settings:
    • Default ERP Budget View: ERP Job Cost Detail Budget
    • Designated Estimated Cost at Completion Column: Estimated Cost at Completion

Which data fields are exported? 

 

What are the requirements?

If you are a Procore + Viewpoint® Spectrum® client, contact Support to enable this feature. The requirements are listed below: