What are the default Variation Request (VR) statuses in Procore?

Answer

This table details Procore's default statuses for a Variation Request (VR) created with the Project level Commitments tool or the Project level Main Contracts tool. Assuming you are using the Procore Standard Budget View, it also shows when contract amounts are reflected in the project's Budget tool.  

Status Definition Contract Amount is reflected in these columns in the Procore Standard Budget View
APPROVED The VR has been 'Approved.' Approved Changes
Draft 1 The VR is in the 'Draft' state. 
Pending - In Review The VR is currently being reviewed by an approved Pending Changes
Pending - Revised The VR was modified since its initial submission. Pending Changes
Pending - Pricing The VR is currently out for pricing.  Pending Changes
Pending - Not Pricing The VR is pending and not actively being priced.  Pending Changes
Pending - Proceeding The VR is pending and work is proceeding.  Pending Changes
Pending - Not Proceeding The VR is pending and no work is taking place.  Pending Changes
Rejected The VR was rejected. 
No Charge The VR is being performed at no charge.

1 This is the default status for a new VR