The following categories of report templates are available to users with the appropriate permissions when they are creating reports in the Company level and Project level Reports tools:

Project Management

  • Overdue Submittals
  • Submittals by Package
  • Open Submittals by Status
  • RFI Average Response Time
  • RFIs by Status
  • Submittals Average Response Time by Responsible Contractor
  • Submittals Procurement
  • Submittals By Responsible Contractor
  • Open Submittals
  • RFIs Average Time Open
  • Open RFIs by Project - Only available in the Company level Reports tool.
  • RFI Questions and Responses
  • Lost Time Report
  • Failed Inspection Items
  • Incident Report
  • Manpower Log
  • Site Diary Completion Report
  • Injury Report
  • Inspection Pass Rate
  • Incident Near Miss
  • Observation Near Miss
  • Open Observations
  • Open Snag List Items
  • Weather Log
  • Accident Log
  • Call Log
  • Delivery Log
  • Notes Log
  • Skip Log
  • Equipment Log
  • Inspection Log
  • Quantity Log
  • Safety Violation Log
  • Visitor Log
  • Waste Log

Financial Management

  • Variation Reconciliation
  • Contracts by Status + Executed
  • Contract Workflow
  • Main PV Line Item Detail - Internal
  • Main PV Line Item Detail By Status - Client
  • Main PV Line Item Detail By Change Reason - Client
  • Contract Values - Summary per Company

Workforce Management

  • Weekly Timesheets by Employee
  • Payroll Report
  • Timesheets by Cost Code
  • Labour by Location
  • Labour Hour Trend
  • Labour Hours by Cost Code