Why am I unable to delete a variation?
Answer
You will not see the option to delete a variation if the variation is already approved. In order to delete an approved variation, you must first unapprove any variations that were approved since that particular variation was approved. For example, if you approved variations in the order of 1,3,4,2,5,6, you will need to unapprove them in the order of 6,5,2,4,3,1. For more information, see Delete a Potential Variation Or Variation Request.
See Also