Transition Steps
Important
No manual steps are required, as all accounts will update automatically on 9 November 2026. However, Procore recommends testing the new list view on a sample test project first, then switching your entire company over whenever you are ready.Follow the step-by-step process to transition your project from legacy list view to the modernised change event list view:
-
Navigate to the Company level Admin tool.
-
Click on Procore Explore.
-
In the Procore Explore catalogue, scroll or search for Modernised change events 2.0.
-
Select the specific project(s) where you want to activate the new view and toggle the feature ON.
-
Note: You can also enable the modernised list view at the Company level through Procore Explore.
-
-
Open the change events tool from the project tools drop-down menu.
-
Confirm that the modernised view is active:
-
Event descriptions are displayed directly below the titles.
-
The new grouped filters panel is available above the list view.
-
-
Click Table settings / Columns to show or hide fields based on team preference.
-
Click the Filters menu to isolate events by status, scope, reason or vendor.
-
Save your column layout and applied filters as a custom view for easy access across your team.