Enable Project Level Budget Code Structure Edits

Objective

To enable a company level setting that allows project users to edit the budget code structure on a project.

Background

Although it is not common for project's to use different budget code structure from project-to-project, a Procore Administrator can configure a setting in the Company Admin tool that allows users with 'Admin' level permissions on a project to change the pattern of the budget code structure for that project.

 Important

If you choose to enable this setting, ensure that your project users are aware of the following limitations:

  • Adding a new company-level segment to the company budget code structure has NO affect on a project's budget code structure. If you want to add the new company-level segment to a project, it must be added manually to the project.
  • You can remove a company-level segment from a project's budget code structure. However, for best results, it is recommended that you remove the segment at the beginning of the project and avoid adding that segment back mid-project. 
  • You can reorder the segments on the project level budget code structure at any time. 

Things to Consider

Steps

  1. Navigate to the company's Admin tool. 
  2. Under 'Company Settings', click Work Breakdown Structure.
  3. Scroll to the 'Budget Code Structure' table. 
  4. Click the Configure Budget Code Structure icons-settings-gear.png icon. 

    wbs-company-admin-cog-budget-code-structure.png
     
  5. In the 'Edit Budget Code Structure at Project Level' window, mark the Enable Project Level Budget Code Structure Edits tickbox. 

    wbs-edit-project-level-budget-code-structure.png
     
  6. Click Save

Next Steps