Configure Settings for Procore Tools in Data Extracts
Background
In the Data Extracts 2.0 tool, you can configure the settings of various Procore tools when creating and editing extracts.
Things to Consider
- Required User Permissions
- Additional Information:
- No settings are available for the Directory, Documents, Photos, Variations and Models tools.
- Attachments associated with the Variations tool's items are included in the extract by default.
- All data for the Models tool is included in the extract by default.
Configure Settings
You can configure the settings of various Procore tools to specify the exact content you want to include in your extract.
| Procore Tools | Settings | Steps |
|
Action Plans |
Attachments |
Select one of these options:
Note: Attachments associated with action plan items are included as separate files by default. |
|
Tendering Change Events Correspondence Emails Forms Incidents Inspections Meetings Main Contract Payment applications Main Contracts Snag List Purchase Orders Subcontractor Payment Applications Subcontracts |
Include Attachments |
Unmark this tickbox if you do not want to include attachments associated with items in the extract. Note: By default, this tickbox is selected. |
|
Site Diary |
Log Status |
Select the status of logs to be included in the extract. Note: 'Approved' and 'Rejected' statuses are included by default. You can remove them if required. |
| Log Type |
Select the type of logs to be included in the extract. Note: All log types are included by default. You can remove them if required. |
|
| Exclude Empty Days |
Unmark this tickbox to include days when the site diaries are not completed. Note: By default, this tickbox is selected. |
|
| Include Attachments |
Unmark this tickbox to exclude attachments associated with site diary items in the extract. Note: By default, this tickbox is selected. |
|
| Month & Year |
Use the < and > buttons to navigate to the required month and year. Note: By default, the current month and year are selected. |
|
| Today | Click Today to view the site diaries starting from today onwards. | |
|
Drawings Submittals |
Include Attachments |
Unmark this tickbox to exclude attachments associated with items in the extract. Note: By default, this tickbox is selected. |
|
Revision |
Select one of these options:
|
|
|
Observations |
Include Attachments |
Unmark this tickbox to exclude attachments associated with Observation items in the extract. Note: By default, this tickbox is selected. |
| Include Linked Drawings |
Mark this tickbox to include drawings linked with Observation items in the extract. Note: Linked drawings are not included by default. |
|
|
RFI |
Include Attachments |
Unmark this tickbox to exclude attachments associated with RFI items in the extract. Note: By default, this tickbox is selected. |
| Include Official Response Only |
Unmark this tickbox to include RFIs regardless of whether they have an official response in the extract. Note: By default, this tickbox is selected. |
|
| Specifications |
Revision |
Select one of these options:
|