Skip to main content
Procore (en-GB)

Import a Main Contract BOQ from a ProEst® XML File

Objective

To import a project's Main Contract's Bill of Quantities (BOQ) into Procore by uploading an exported XML file from ProEst®.

Things to Consider

  • Required User Permission:
    • To submit a request to enable imports from ProEst, your company's Procore Administrator must submit a request to your company's Procore point of contact. 
    • To import a Bill of Quantities (BOQ) from ProEst into the Main Contracts tool, 'Admin' on the Main Contracts tool
  • Additional Information:
    • By default, the ProEst by Procore integration is disabled for new Procore accounts. 
    • Project data is not synchronized between your project in ProEst and Procore. If you make changes to the estimate in ProEst, you'll need to upload a revised version into Procore if you want the line items to match.
    • ProEst cost codes must exactly match the cost codes in Procore.

Steps

Export a Project Estimate from ProEst

If you do not have an XML file of the estimate from your ProEst project, complete the steps in Export a Project Estimate from ProEst.

Import a ProEst XML File into Procore

  1. Navigate to the project's Main Contracts tool.
  2. Locate the main contract that you want to use for the import in the list.
  3. Click Edit.
  4. Click the Bill of Quantities tab.
  5. Click Edit.
  6. Specify whether you want the line items to be separated by division or subdivision.

    import-proest.png
  1. Select the XML file and click the Import button.
  2. Wait a few seconds for the file to be uploaded into Procore. Click the Bill of Quantities tab to refresh the contents.
  3. Verify that all of your estimate's line items were imported.
  4. If necessary, you can make further changes to the BOQ by clicking Edit.
    • Manually add additional line items
    • Delete a line item
    • Change the selected cost code number
    • Edit a line item's description, type and contract amount
      If the combination of the sub job, cost code and cost type are non-budgeted for a line item, this line item will be added directly to the Budget with a "?" next to the line item. See Add a Partial Budget Line Item.
  5. Click Save. (Use the Save and Email button if you want to save your changes, as well as forward a copy of the Main Contract using Procore's built-in email feature. You'll also be able to specify recipients and include a brief message about the Main Contract and its BOQ.)