Objective

To view the change history of an RFI in the project's RFIs tool. 

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's RFIs tool. 

Steps

  1. Navigate to the project's RFIs tool.
  2. Locate the desired RFI in the list. Click View
  3. Click the Change History tab. 
    • Date. The date and time the change was made. 
    • Action By. The user who performed the change. 
    • Changed. Details the change that was made.
    • From. Depending on the change made, this field shows different information. For example, if the assignee was changed from one user to another, this field would show the previous assignee. 
    • To. Depending on the change made, this field shows different information. For example, if the assignee was changed from one user to another, this field would show the new assignee.