At what tier can an owner approve a Main Contract Variation (MCV)?

Answer

The variation tier setting configured for the Main Contracts tool only affects the number of tiers used for the overall change management process.  An owner can always be marked as a designated 'Reviewer' on a MCV when you want it to be approved by an owner. To learn how to approve a MCV as an owner, see Approve or Reject Main Contract Variations (PCCOs).

 Tip

If your project is configured for 2-tier or 3-tier variations and your project team wants an owner to review variation information at an earlier point in the overall change management process,  you can email a Potential Variation (PV) or Variation Request (VR) to an owner. For instructions see the links below:

When configuring the number of main contract variation (MCV) tiers for the Main Contracts tool, a user with 'Admin' permission on the tool can choose between a 1-tier, 2-tier-, or 3-tier configuration. See What are the different variation tiers?