Skip to main content
Procore

What happens when 'Restrict Non-draft edits to Contracts and Variations' and 'Enable Always Editable Bill of Quantities' are both enabled?

Answer

These two settings: 'Restrict non-draft edits to Contracts and Variations' and 'Enable Always Editable Bill of Quantities' are both used to determine whether edits can be made to a contract or variation's bill of quantities once they are no longer in a 'Draft' status. The 'Restrict non-draft edits to Contracts and Variations' setting is a company level configuration that is used to prevent edits to 'Bill of Quantities' and 'Contract Company' settings across every project in a company's Procore account. However, the 'Enable Always Editable Bill of Quantities' setting is configured at the project level within the Commitments and Main Contracts tool configuration settings. 

Since the company level setting restricts edits and the project level setting allows them, they oppose each other when they are both enabled at the same time. 

If both of these settings are enabled, the 'Enable Always Editable Bill of Quantities' setting will override the 'Restrict non-draft edits to Contracts and Variations' Company Level setting and edits to Contract and Variation Bill of Quantities will be allowed.

See Also