What’s the difference between sequential and parallel approval in the submittal workflow?

Answer

In January 2018, Procore deployed a new submittal workflow model to provide your users with more flexibility when setting the approval path for a submittal. This deployment is complete and the new model prevents project users with 'Admin' level permission on the Submittals tool from having to specifically configure the tool to use sequential approval or parallel approval. A new submittal workflow table has been implemented on all Procore accounts and allows your users to create and edit submittals that use either sequential, parallel or a combination of both approval models:

Examples

sequential approval Steps

If you want the submittal workflow to use sequential approval, add only one (1) user to each line item in the workflow. You can add multiple line items to a workflow and each line item will be processed by Procore in sequential order. The following example shows you how to create a sequential approval workflow that includes one (1) line item on a workflow that contains four (4) reviewers total. 

demo-sequential-workflow.gif

Parallel Approval Steps

If you want to use parallel approval on a submittal, add two (2) or more people to a line item. You can add multiple line items to a workflow and each line item will be processed by Procore in sequential order. The following example shows you how to create a parallel group of approvers. Note: When using parallel approval, the Approver role is the only role available. The Submitter role cannot be selected.
 

demo-parallel-only.gif

Combined Sequential and Parallel Approval Steps

If you want a step in the submittal workflow to use sequential approval, add only one (1) user to each line item in the workflow. You can add multiple steps to a workflow and each line step will be processed by Procore in sequential order. If you want a step in the new submittal workflow to use parallel approval, simply add two (2) or more users to that step. There are three (3) sequential approval steps in the example below, but the third step has two (2) users in parallel. When a step is processed in parallel, all members of the group must submit a response before the Action Required By responsibility shifts to the next step, unless the user marked as required responders.  

demo-sequential-parallel.gif

Details

  1. Under Submittal Workflow, do the following for each desired line item in the submittal:
    • Name. Start typing a project user's name in the Search box. Then select the appropriate user from the list.
      • If you want to require a response from the user, place a mark in the checkbox next to their name.
        OR
      • If you do NOT want to require a response from the user, remove the mark from the checkbox.
        Note: If you are adding more than one user to a parallel approval workflow group, the Action Required By Responsibility will shift to the next workflow group after all of the people marked required in the group submit a response to the submittal. 
    • Role. Select Approver or Submitter from the list. See What is the difference between a submitter and approver in submittals?
      Notes:
      • To be designated as an approver, the person must exist in the Project level Directory tool (see Add a User Account to the Project Directory) and must also be granted 'Admin' or 'Standard' level permissions to the Submittals tool (see Set User Permissions for the Submittals Tool).
      • If you are a user with 'Standard' level permissions to the Submittals tool, you can only add users with 'Admin' level permissions to the workflow.
      • If you plan to add a Submitter to the submittal, we recommend that you designate a Submittal Manager as the first approver in the submittal's sequential approval workflow. This gives the Submittal Manager an opportunity to ensure the submittal is thoroughly reviewed by your internal stakeholder before it is sent to the users in the next step on the submittal workflow. 
      • If you are a user with 'Admin' level permissions to the Submittals tool, you can add users with either 'Admin' or 'Standard' level permissions to the workflow. 
        Note: If you want the submittal workflow to use sequential approval, add only one user to each line item in the workflow. If you want a step in the submittal workflow to use parallel approval, add two or more users to a line item. 
    • Due Date. Select a date from the calendar for the submittal response to be due.
      Note: The 'Due Date' field is automatically populated based on the default number of days specified on the Submittals tool's Configure Settings page. See Configure Settings: Submittals Tool. The due date also respects which days are set as 'working days' for the project. See Set Project Working Days.
  2. Click Add Step. 
  3. Repeat these steps to add another user to the workflow. 
  4. If you want to change the order of the workflow steps, do the following:
    1. Grab the line item by the vertical grip (⋮⋮).
    2. Use a drag-and-drop operation to move the line item into the desired order. 

      submittals-change-order-table.png