Navigate to the project's Schedule tool using an Android mobile device.
Tap the programme task you want to update.
Tap Edit.
Note: Percent Complete cannot be updated for Summary programme tasks or Milestones.
Enter the current Percent Complete for the task and tap Done.
Note: You can enter a numeric value from 0 to 100. The value you enter must be a whole number.
Tap Save.
The programme task on the mobile device updates to show the amount you entered for Percent Complete. Note: These changes are also shown in the Programme tool on the web application.