Skip to main content
Procore

(Beta) Create Client Contract Variations

 In Beta
This content is for participants in the Project Financials: Modernised Experience for Main Contracts beta program. 
 Limited Release
flag-us.png  The Client Contracts tool is available as a limited release for Procore customers in the United States who have implemented the Procore for Speciality Contractors point-of-view dictionary. To learn more, see What tool names and terms are different in Procore for main contractors, owners and speciality contractors?

Objective

To create a client contract variation in Procore's Client Contracts tool. 

Background

Use the steps below when you want to create a variation for a client contract.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's Client Contract's tool.
  • Additional Information:
  • For companies using the icon-erp-synced2.png ERP Integrations tool: Show/Hide  

Steps

  1. Navigate to the project's Client Contracts tool.
  2. Locate the client contract to work with. Then click its Number link. 
  3. Click Create and choose the Create Contract VAR option.
  4. Complete the following fields:
    • Sign with DocuSign©
      If the Procore + DocuSign© integration is enabled, a tick appears by default. Clear the tick from the box if you do NOT want to collect signatures with DocuSign©
       Tip
      How do you collect signatures with DocuSign? After the data entry for the subcontract is complete, change its status to 'Approved' and click the Complete with DocuSign button. This launches the DocuSign® application. If you have not previously signed in, you will be prompted to Sign In to DocuSign®. After you are signed in, you can proceed with Prepare a DocuSign® Envelope for Signature
    • Variation #
      Accept the default contract number, enter a new number for this variation or create a custom numbering scheme future variations.
       Notes
      • If you plan to create multiple variations, Procore automatically assigns new numbers in sequential order. For example; 001, 002, 003 and so on. 
      • To use a custom numbering scheme, enter any set of alphanumeric characters and Procore automatically assigns new numbers in sequential order using your custom scheme. For example, enter CCV-1, CCV-01 or CCV-001. 
    • Date Created
      Shows the date and time the variation was created. You cannot change this date.
    • Revision
      Displays the variation's revision number. When a variation is first created, its revision number is zero (0). A variation could have multiple revisions because of feedback from a reviewer/approver. 
    • Created By
      Displays the name of the user that created the variation. You cannot change this name.
    • Title
      Enter a title for the variation. 
    • Status
      Select the current status of the variation. To learn more, see What are the default statuses for variations in Procore? 
    • Private
      Mark this tickbox if you want to make the variation 'Private' and visible only to users with 'Admin' on the Client Contracts tool. 
    • Due Date
      Select a due date for when the variation must be approved by. 
    • Issued Date
      Select the date when the variation was issued.
    • Designated Reviewer
      Select the Procore user at your organisation who is responsible for approving or rejecting the variation. To appear as a selection in this list, the designated reviewer's Procore user account must be added to the Project Directory and have 'Standard' level permissions or higher on the project's Client Contracts tool. See Add a User Account to the Project Directory
       Tip
      Are you the 'Designated Reviewer' on a variation? To learn how to submit an approve or reject response, see Approve or Reject Client Contract Variations
    • Paid Date
      Select the date that payment was received for the variation.
    • Description
      Enter a more detailed description of the variation.
    • Programme Impact
      If this variation is expected to impact the construction project's programme, enter the estimated number of additional days this would add to the programme. 
    • Revised Substantial Completion Date
      Enter an updated substantial completion date for the project. 
       Note
      If the substantial completion date is enabled on the Client Contracts tool, Procore updates the variation's 'Revised Substantial Completion Date' field after the variation is placed into the Approved status. See Configure Settings: Client Contracts
    • Executed
      Mark this tickbox after the variation is fully executed.
    • Variation Requests
      If the Client Contracts tool is configured for three (3)-tier variations, select any variations related to this variation from this drop-down list. See Configure the Number of Client Contract Variation Tiers
    • Potential Variations
      If the Client Contracts tool is configured for two (2)-tier variations, select any potential variations related to this variation from this drop-down list.  See Configure the Number of Client Contract Variation Tiers
  5. Choose one (1) of these options:
    • To create the variation, click Create.
      OR
    • To create the variation and send email notifications, click Create & Email