Objective
To change a drawing version's number to an existing drawing's number.
Background
There might be a situation where a drawing version was assigned the incorrect number during the upload review process and you may want to change the version's drawing number to an existing drawing's number.
When you change a drawing number of a single version, you re-associate the version with an existing drawing in your project. The version that you've re-associated will no longer appear in the original drawing's Versions section and will instead be associated with the new drawing that you've selected.
Things to Consider
- Required User Permissions:
- 'Admin' level permission on the project's Drawings tool.
- Additional Information:
- A drawing with the number you want to assign this version to must already exist in the project's Drawings tool.
- If you want to edit the drawing number of all versions of the drawing, see Edit Drawings.
- If you want to reorder revisions of the drawing, click the grip handle icon next to a drawing version and use a drag-and-drop operation to change the order. See Reorder Revisions of a Drawing.
Steps
- Navigate to your project's Drawings tool.
- Click Info next to the drawing you want to change the drawing version number for.
Note: Drawings that have one or more versions have the number of each version in the 'Revision No.' column. - In the 'Versions' section, click the vertical ellipsis (⋮).
- Click Change drawing number.
Note: The Change Drawing Number modal will appear. - Fill in the following fields:
- Drawing No.: Select from the drop-down menu the drawing number that you want to associate with this version.
Note: To quickly find a drawing in the menu, begin typing the number or title of the drawing in the search bar. - Versions:
In this section, you will see all of the versions of the drawing you selected.- If necessary, reorder the versions by dragging and dropping the version you're re-associating to the correct place.
- Revision No.: If necessary, enter a new revision number.
Note: You will need to edit the revision number if the revision number has already been taken by an existing version of the selected drawing.
- Drawing No.: Select from the drop-down menu the drawing number that you want to associate with this version.
- Click Ok.
Note: You will see a confirmation modal when the version has been successfully moved to the new drawing number. - Click Done.