Skip to main content
Procore

Enable Financial Markup on a Main Contract

Objective 

To enable Procore's financial markup capabilities on a main contract.

Background 

You can enable financial markup capabilities on individual main contracts. This gives your project user's the ability to apply financial markup to MCVs associated with a commitment as described in Add Financial Markup to Main Contract Variations.

Things to Consider 

  • Required User Permissions:
    • 'Admin' level permissions on the project's Main Contracts tool.

Steps 

  1. Navigate to your project's Main Contracts tool.
  2. Locate the contract to work with. Then click its Number link.
  3. In the contract, click the Advanced Settings tab.
  4. Click the Edit button.
  5. Under 'Financial Markup Settings', mark the Enable Financial Markup checkbox.
  6. Click Save.