Objective

To export the snag list log as a CSV.

Things to Consider

  • Required User Permissions: 'Read Only,' and above level permissions on the project's Snag List tool.
  • Additional Information:
    • Use the Snag List filters (e.g. Assignee Company, Location, Type, etc.) to focus attention on specific snag list item and limit total page length. For example, you may want to export contractor-specific CSVs.

Steps

  1. Navigate to the project's Snag List tool.
  2. Click Export.
    export-punch-list-log.png
  3. Click CSV.
  4. A CSV file will download to your computer's default 'Downloads' folder containing a concise summary of the snag list items in your log. The CSV will include the following information:
    • Title
    • Type
    • Detail
    • Assignee Company
    • Assignee Name
    • Assignee Response
    • Date Initiated
    • Due Date
    • Location
    • Reference
    • Priority
    • Cost Code
    • Cost Impact
    • Cost Impact Amount
    • Programme Impact
    • Programme Impact Days
       

 

If you would like to learn more about Procore's punch list software and how it can help your business, please visit our construction punch list software product page icon-external-link.png.