Import a Project Programme

Background

Importing your programme centralises your project's timeline, allowing the entire team to access the most current data in one place.

Things to Consider

  • Required User Permissions: 'Standard' level permissions or higher on the project's Scheduling tool.

  • Additional Information:

    • Supported File Types: Procore supports .ppx (Phoenix), .mpp (Microsoft Project) and .xer (Primavera P6).

    • New Beta Formats: As of July 21, 2026, native file imports are now supported in Open Beta for Asta Powerproject (.pp) and MS Project XML (.xml/ MSPDI). Note that Asta .pp and MS Project. xml` support import only; exports are not available. Go to Manage Features With Procore Explore to join the beta.

    • Smartsheet users must export to XML first (file-based import, not direct API).

    • When importing, the project calendar is carried over directly from the native source file.

    • Note for Oracle Primavera Cloud (OPC) Users: For .xer files generated via OPC that lack unique GUIDs, Procore now utilises a fallback identification strategy mapping Activity IDs and System-generated Object IDs. This ensures lookaheads and tool integrations (like Submittals) stay fully intact across successive re-imports.

 

 Important
At this time, the latest cloud versions of P6 .xer files are not supported.

Steps

  1. Navigate to the project's Scheduling tool.

  2. Click Import.

  3. Click Attach File(s) and select your programme file or drag-and-drop the file into the upload area.

  4. Click Import.