Add a Related Item to a Submittal Package

Objective

To associate related items to a submittal package using the Project level Submittals tool.

Background

When approvers and interested parties review a submittal package, it may be helpful for them to have all the information they need (e.g., tender, variations, documents, drawings, snag items, RFIs and more) to make informed decisions and take informed action.  

In Procore, a Related Item is a link between two Procore objects. It is an option that's available in many Procore tools, such as Commitments, Documents, RFIs, Submittals and Transmittals. For example, if you are creating a submittal, you might add a Procore drawing of the installation location or a photo of the item to be installed as a related item on the submittal. If you are adding a new snag item, you might link a Potential Variation (PV) or a Commitment Variation (CV) as a related item, so the subcontractor can view the costs associated with the snag item. 

In the Submittals tool, you can also add related items to your submittal packages (see Create a Submittal Package). This helps you keep the information associated with your submittal package organised. It also provides responsible contractors and reviewers access to the information they may need in reference to the package. 

Things to Consider

Steps

  1. Navigate the project's Submittals tool.
  2. Click Packages.
  3. Locate the desired submittal package and click View.
  4. Click the Related Items tab. 
  5. Next to the 'Related Items' table, click Edit.
  6. Add the related item to the package as follows:

    add related items to submittal package.png
     
    • Type: Select an item type for the related item from this list. For example, if you want to add a tender sheet, select Tender. The selections available in this list will depend upon which Procore tools are active on the project. See Add and Remove Project Tools.
    • Description: Select the appropriate item from the list. For example, if you are adding a tender sheet, a list of all the tender sheets for the project is available. 
    • Date: This date populates automatically with the current date. 
    • Notes: Type any details about the related item. 
  7. Click + Add.
    Notes:
    • If the Add button does not appear on the page, you must go back and select a Type and Description 
    • You can add one related item per line item.
    • You can add as many line items as desired. 
  8. Click Save.
    The system places the submittal back into view mode and your new item(s) will be listed the 'Related Items' tab of the submittal package. 