Can I update the Percent Complete field on the Procore web application?
Background
Most items in an imported programme task must be updated in the programme's native application and then be uploaded again to the project's Programme tool in Procore. However, users can update the Percent Complete for imported programme tasks from the project's Programme tool using the Procore mobile application.
Answer
No. The Percent Complete field for the Project level Programme tool can currently only be updated from the Procore mobile application. See Update the Percent Complete for a Programme Task (iOS) or Update the Percent Complete for a Programme Task (Android).