Skip to main content
Procore (en-GB)

Update the Percent Complete for a Programme Task (iOS)

Objective

To update the Percent Complete field in the project Programme tool using an iOS mobile device.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the Project level Programme tool.
      OR
    • 'Read Only' or 'Standard' level permissions with the 'Update Task Completion Percentages' granular permission enabled on the permission template.  
  • Additional Information:
    • If a programme is modified in its native application, the changes will not show in Procore unless you export the CSV file and upload it again to the project's Programme tool in the Procore web application. 
    • Percent Complete cannot be updated for Summary programme tasks or Milestones.
    • Percent Complete for calendar items cannot be updated in the mobile application. 

Prerequisites 

Steps

  1. Navigate to the project Schedule tool using an iOS mobile device.
  2. Tap the programme task you want to update. 
  3. Tap Edit
    edit-schedule-item-ios.png
    Note: Percent Complete cannot be updated for Summary programme tasks or Milestones.
  4. Enter the current percent complete for the task and tap Done. 
    Note: You can enter a numeric value from 0 to 100.  The value enter must be a whole number.
  5. Tap Save.
    save-scheduled-item-ios.png
  6. The programme task on the mobile device updates to show the amount you entered for Percent Complete. 
    schedule-item-percent-saved-ios.png
    Note: These changes are also shown in the Programme tool on the web application.