Update the Percent Complete for a Programme Task (iOS)

Objective

To update the Percent Complete field in the project Programme tool using an iOS mobile device.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the Project level Programme tool.
      OR
    • 'Read Only' or 'Standard' level permissions with the 'Update Task Completion Percentages' granular permission enabled on the permission template.  
  • Additional Information:

Prerequisites 

Steps

  1. Navigate to the project Schedule tool using an iOS mobile device.
  2. Tap the programme task you want to update. 
  3. Tap Edit
    edit-schedule-item-ios.png
    Note: Percent Complete cannot be updated for Summary programme tasks or Milestones.
  4. Enter the current percent complete for the task and tap Done. 
    Note: You can enter a numeric value from 0 to 100.  The value enter must be a whole number.
  5. Tap Save.
    save-scheduled-item-ios.png
  6. The programme task on the mobile device updates to show the amount you entered for Percent Complete. 
    schedule-item-percent-saved-ios.png
    Note: These changes are also shown in the Programme tool on the web application.