What are the different RFQ statuses and how do they affect cost and variation amounts?
Answer
Below is a list of available Request for Quote (RFQ) statuses. Some status changes occur automatically and some must be manually change by a user. Some status changes also automatically update the 'Action required by' person assigned to the RFQ. Some status changes also affect the 'Latest Cost' amount for a change event line item and the amount is automatically updates in the project's variations.
Automatic vs. Manual Status Changes
Automatic Status Changes
The followin status changes occur automatically. They can also be changed by user with 'Admin' level permissions on the Change Events tool:
- Out for Pricing
This status occurs when the RFQ is issued. The Action required by is the RFQ recipient/assignee. RFQs in this status will not affect the Latest Cost. - Under Review
This status occurs when the RFQ response is submitted with a cost and/or programme impact and has not yet been reviewed. The Action required by is the RFQ creator. RFQs in this status will not affect the Latest Cost and the value will not be pulled into a corresponding variation. - Closed
This status occurs when the RFQ is submitted as "No Impact." There is no Action required by for this status. RFQs in this status will affect the Latest Cost and the value will be pulled into a corresponding variation.
Manual Status Changes
- Pending Final Approval
Select this status if you have reviewed the RFQ response. There is no 'Action required by' assignment for this status. RFQs in this status affects the Latest Cost and the value is automatically populated into any variations that are created. - Revise & Resubmit
Select this status if you need the subcontractor to revise the cost/programmeimpact. The Action required by is the RFQ recipient/assignee. RFQs in this status will not affect the Latest Cost and the value will not be pulled into a corresponding variation. - Withdrawn
Select this status if you no longer need pricing from the subcontractor. There is no Action required by for this status. RFQs in this status will not affect the Latest Cost and the value will not be pulled into a corresponding variation.
Available RFQ Statuses
The following table details each status.
Out for PricingAutomatically Updated |
Under ReviewAutomatically Updated |
ClosedAutomatically Updated |
Pending Final ApprovalManually Updated |
Revise and ResubmitManually Updated |
WithdrawnManually Updated |
---|
Action required by | Assignee | Creator | None | None | Assignee | None |
Intent | This status occurs when the RFQ is issued. | The RFQ response is submitted with a cost and/or programme impact and has not yet been reviewed. | The RFQ is submitted as "No Impact". | You have reviewed the RFQ response. | Need the subcontractor to revise the cost/programme impact. | No longer need pricing from the subcontractor. |
Affects Latest Cost | ||||||
Value to Populate Commitment Cost/VAR | Cost ROM | Cost ROM | RFQ Value | RFQ Value | Cost ROM | Cost ROM |
Value to Populate Main VAR | Revenue ROM | Revenue ROM | Revenue ROM | Revenue ROM | Revenue ROM | Revenue ROM |
Attachments Carry to VARs |
Notes
- If a change event line item Revenue ROM is set to “Automatically Follow Latest Cost”, then the RFQ status will also affect the Latest Cost that pulls into the Revenue ROM.
- If a Main VAR is created for a change event line item, that value will override the RFQ value on Commitment Cost/VAR creation.