Create a Commitment Variation from a Change Event
Objective
To create a commitment variation from a change event.
Background
In Procore, a change event is any change that affects the scope of a construction project. See What is a change event? Once a change event is recorded in Procore, project teams have the option to create a Request for Quote (RFQ) to obtain quotes from the responsible contractors. See Create RFQs from a Change Event.
You can create a commitment variation from a change event either before or after the associated RFQ has been responded to or reviewed. However, if you wait until after the RFQ has been reviewed and the RFQ status is set to 'Pending Final Approval,' the variation's Bill of Quantities (BOQ) automatically populates with the amounts from the RFQ during the variation creation process. For more information about RFQ statuses, see What are the different RFQ statuses and how do they affect cost and variation amounts?
The process you use when managing changes in Procore also depends upon how your project's commitment variation tiers are configured. To learn more, see What are the different variation tier settings in Project Financials?
- If your project is using the one (1) tier variation configuration, you will only need to create a CV. See Create a Commitment Variation. Note: If you are using the DocuSign integration, please see Complete a Commitment Variation with DocuSign® instead.
- If your project is using the two (2) tier variation configuration, first you will Create a Commitment Potential Variation from a Change Event. Next, you will create a CV from the Commitments tool. See Create a Commitment Variation.
Things to Consider
- Required User Permissions:
- 'Standard' level permissions or higher on the project's Change Events tool
AND - 'Admin' level permissions on the project's Commitments tool.
- 'Standard' level permissions or higher on the project's Change Events tool
Steps
- Navigate to the project's Change Events tool.
- Select one or more change event line items you want to include in the variation.
Note: You can select line items across multiple change events. You can also use the Filter drop-down to filter by vendor. - Choose Bulk Actions > Create a Commitment VAR.
Note: The line items on the variation's BOQ is created from line items on the change event. - Complete the following information:
- Number
This field automatically populates based on the number of variations already created. By default, the number will automatically increment by one.Tip
How does Procore assign numbers to commitment variations? To learn more, see Can I customise the numbering system for financial objects in Procore? - Revision
This field displays the variation's revision number. When a variation is first created, its revision number is zero. A variation could have multiple revisions because of feedback from a reviewer/approver. This field must be manually entered as revisions are not automatically tracked. - Title
This field will automatically populate with the name of the change event. - Status
Select the current state of the variation. Procore's default status is Pending-In Review.Note
Which statuses are available with commitment variations? For details, see What are the default statuses for variations in Procore?
- Private
Check this box so only you and users with 'Admin' level access on variations can view this variation. - Change Reason
The change reason field will populate with the change reason you selected in the change event; however, you can edit as necessary. Select the reason for the potential variation, either Client Request, Design Development, Allowance, Existing Condition, Backcharge or any options customised by the Procore Administrator. Set the Default Change Management Configurations. - Accounting Method
This field inherits the accounting method that was specified in the Commitment (e.g. Amount Based). - Due Date
Enter the date the variation is due. - Issued Date
Enter the date the variation was issued. - Paid Date
Enter the date the variation was paid. - Designated Reviewer
Select a user to review the variation. - Request Received From
Select a user from the project's directory who you are submitting the potential variation on behalf of. - Description
Enter a more detailed description of the variation. - Programme Impact
If known, you can provide an estimate of the number of additional days that would potentially be added to the current project programme if the variation were approved. - Location
Use the location drop-down menu to select a location the [item] impacts. Either select from the predefined locations or see How do I add a multi-tiered location to an item? This location may be as general as the site location at the first tier or as specific as where on the site the contractor will be working at the second tier. - Reference
Reference any other tools, materials, drawings or documents that are related to the potential variation. - Executed
Check this box once the variation has been completed. - Field Change
Check this box if the variation is a field change. - Paid in Full
Check this box to indicate you have received payment for this change. - Change Event Line Items
If your project is integrated with ERP, select a line item from the associated line item drop-down menu. If you select New Line Item, a zero (0) pound line item will be added to the commitment's Bill of Quantities. If your project is not integrated with ERP, you can skip this action and create the variation. - Attachment
Attach any relevant documentation. Note: If there is an associated Request for Quote (RFQ) and the reviewer has attached any documentation to their RFQ response, the Change Events tool can be configured to add those attachments to new variations. See Configure Advanced Settings: Change Events.
- Number
- Click Create. The Bill of Quantities for the variation will be created from the change event line items. You can click into the Bill of Quantities tab to verify your line items.
Note
Change Event line items by default will pass the latest cost amount to the Commitment Variation Bill of Quantities line items.
If a Main Contract Variation was associated with that Change Event Line item before the creation of the Commitment Variation, the Change Event line item will then pass the Latest Price amount to the Commitment Variation Bill of Quantities line item.