Background

In a Procore budget or forecasting view, a source column pulls source data from corresponding columns in the Financial Management tools. Some source columns also have advanced options. To configure source columns for a budget or forecasting view, see Create a budget view or Create a forecasting view.

Example

This image shows the source column configuration options in the 'Column details' panel when configuring a column. When options are available, users can select data sources from drop-down lists, mark tickboxes to select options and set applicable filter criteria from drop-down lists.

Answer

When configuring a new or existing Source Column in a Budget or forecasting view, you can mark one or more tickboxes to turn the corresponding data columns ON. Remove the ticks to turn columns OFF. Users can also configure group and filter options for source columns when available.

Column Source

Source Tool

Data Column

Group or filter options

Budget Change Production Qty

Budget

Budget Change Production Quantities

  • Scope

  • Status

Budget Change Unit Quantity

Budget

Budget Change Unit Quantity

Status

Budget Changes

Budget

Budget Change Adjustments

  • Status

  • Change event scope

Budgeted Production Quantity

Budget

Budgeted Production Quantity

N/A

Change Event Production Qty

Change Events

ROM (Rough Order of Magnitude)

  • Scope

  • Change Event Status

Change Event Unit Qty

Change Events + Variations

Revenue ROM (Rough Order of Magnitude)

  • Main contract PV

  • Scope

  • Change Event Status

Change Event Unit Qty

Change Events + Variations

ROM (Rough Order of Magnitude)

  • Main contract PV

  • Commitment cost

  • Non-Commitment Costs

  • Scope

  • Change Event Status

Change Events

Change events + variations (2- or 3- tier required)

Revenue ROM (Rough Order of Magnitude)

  • Amount

  • Main contract PV

  • Scope

  • Change Event Status

Change Events

Change events + variations (2- or 3- tier required)

ROM (Rough Order of Magnitude)

  • Main contract PV

  • Commitment Cost

  • Non-Commitment Costs

  • RFQ

  • RFQ Status

  • Change Event Status

  • Scope

Change Events

Change Events

Budget ROM (Rough Order of Magnitude)

Budget Changes

Change Events

Change events + variations (2- or 3- tier required)

RFQ (Request for Quote)

  • Main contract PV

  • Commitment cost

  • Non-Commitment Costs

  • Scope

  • Change event status

  • RFQ Status

Change Events

Change Events

Change Event Latest Cost

  • Amount

  • Scope

  • Change Event Status

Change Events

Change Events

Change Event Latest Price

  • Amount

  • Scope

  • Change Event Status

Commitment

Commitments

Subcontracts

Status

Commitment

Commitments

Purchase Order Contracts

Status

Commitment

Commitments

Variations (CVs)
Advanced options: variation requests and potential variations can be filtered by status or scope.

  • Status

  • Scope

Direct Costs

Direct Costs

Direct Costs

  • Type

  • Status

Direct Costs Unit Qty

Direct Costs

Direct Costs Unit Quantity

  • Type

  • Status

Equipment Timecard Hours

Equipment

Equipment Timecard Hours

N/A

ERP Job Costs

ERP Integrations

  • ERP Job to Date Costs

  • ERP Commitment Invoiced

  • ERP original budget

  • ERP current budget

N/A

Installed Production Quantity

Budget

Installed Production Quantity

N/A

Owner Payment Applications

Main Contracts

Owner Payment Applications

  • Amount

  • Markup

  • Status

Main Contracts

Main Contracts

Main Contracts

Status

Main Contracts

Main Contracts + Variations

Variations (MCVs) advanced options:
Variation requests and potential variations can be filtered by status or scope.

  • Status

  • Scope

Main Production Qty

Main Contracts + Variations

Variations production quantity Advanced options: Variation requests production quantity and potential variations production quantity can be filtered by status or scope.

  • Status

  • Scope

Main Unit Qty

Main Contracts + Variations

Variations (MCVs) unit quantity Advanced options:
Variation requests unit quantity and potential variations unit quantity can be filtered by status or scope.

  • Status

  • Scope

Production Quantities

Budget

Budget production quantity

N/A

Production Quantities

Budget

Budget Change Production Quantities

  • Scope

  • Status

Production Quantities

Main Contracts + Variations

Main contract variations production quantity
Advanced options: Main contract variation request production quantity and main contract PV production quantity can be filtered by status or scope.

  • Status

  • Scope

Production Quantities

Change Events

Change event production quantity rough order of magnitude

  • Scope

  • Change Event Status

Production UOM

Budget

Budgeted Production UOM

N/A

Subcontractor Payment Applications

Commitments

Subcontractor Payment Applications

  • Amount

  • Markup

  • Status

Timecard Entry Hours

Timecard

Timecard Entry Hours