What source columns are available in Procore's budget or forecasting views?
Background
In a Procore budget or forecasting view, a source column pulls source data from corresponding columns in the Financial Management tools. Some source columns also have advanced options. To configure source columns for a budget or forecasting view, see Create a budget view or Create a forecasting view.
Example
This image shows the source column configuration options in the 'Column details' panel when configuring a column. When options are available, users can select data sources from drop-down lists, mark tickboxes to select options and set applicable filter criteria from drop-down lists.
Answer
When configuring a new or existing Source Column in a Budget or forecasting view, you can mark one or more tickboxes to turn the corresponding data columns ON. Remove the ticks to turn columns OFF. Users can also configure group and filter options for source columns when available.
|
Column Source |
Source Tool |
Data Column |
Group or filter options |
|---|---|---|---|
|
Budget Change Production Qty |
Budget |
Budget Change Production Quantities |
|
|
Budget Change Unit Quantity |
Budget |
Budget Change Unit Quantity |
Status |
|
Budget Changes |
Budget |
Budget Change Adjustments |
|
|
Budgeted Production Quantity |
Budget |
Budgeted Production Quantity |
N/A |
|
Change Event Production Qty |
Change Events |
ROM (Rough Order of Magnitude) |
|
|
Change Event Unit Qty |
Change Events + Variations |
Revenue ROM (Rough Order of Magnitude) |
|
|
Change Event Unit Qty |
Change Events + Variations |
ROM (Rough Order of Magnitude) |
|
|
Change Events |
Change events + variations (2- or 3- tier required) |
Revenue ROM (Rough Order of Magnitude) |
|
|
Change Events |
Change events + variations (2- or 3- tier required) |
ROM (Rough Order of Magnitude) |
|
|
Change Events |
Change Events |
Budget ROM (Rough Order of Magnitude) |
Budget Changes |
|
Change Events |
Change events + variations (2- or 3- tier required) |
RFQ (Request for Quote) |
|
|
Change Events |
Change Events |
Change Event Latest Cost |
|
|
Change Events |
Change Events |
Change Event Latest Price |
|
|
Commitment |
Commitments |
Subcontracts |
Status |
|
Commitment |
Commitments |
Purchase Order Contracts |
Status |
|
Commitment |
Commitments |
Variations (CVs) |
|
|
Direct Costs |
Direct Costs |
Direct Costs |
|
|
Direct Costs Unit Qty |
Direct Costs |
Direct Costs Unit Quantity |
|
|
Equipment Timecard Hours |
Equipment |
Equipment Timecard Hours |
N/A |
|
ERP Job Costs |
ERP Integrations |
|
N/A |
|
Installed Production Quantity |
Budget |
Installed Production Quantity |
N/A |
|
Owner Payment Applications |
Main Contracts |
Owner Payment Applications |
|
|
Main Contracts |
Main Contracts |
Main Contracts |
Status |
|
Main Contracts |
Main Contracts + Variations |
Variations (MCVs) advanced options: |
|
|
Main Production Qty |
Main Contracts + Variations |
Variations production quantity Advanced options: Variation requests production quantity and potential variations production quantity can be filtered by status or scope. |
|
|
Main Unit Qty |
Main Contracts + Variations |
Variations (MCVs) unit quantity Advanced options: |
|
|
Production Quantities |
Budget |
Budget production quantity |
N/A |
|
Production Quantities |
Budget |
Budget Change Production Quantities |
|
|
Production Quantities |
Main Contracts + Variations |
Main contract variations production quantity |
|
|
Production Quantities |
Change Events |
Change event production quantity rough order of magnitude |
|
|
Production UOM |
Budget |
Budgeted Production UOM |
N/A |
|
Subcontractor Payment Applications |
Commitments |
Subcontractor Payment Applications |
|
|
Timecard Entry Hours |
Timecard |
Timecard Entry Hours |
Status |