Add Plan Revisions Entries (Android)

Also available on  ios-gray-icon.jpg  web-gray-icon.jpg

Objective

To add Plan Revisions entries to the Site Diary using the Procore app on an Android mobile device. 

Things to Consider

  • Required User Permissions:
    • 'Standard' or 'Admin' level permissions on the project's Site Diary tool.
  • Additional Information:
    • Procore recommends that you use the Drawings tool to track plan revisions and changes to the project's drawings.
  • This action can be performed in offline mode. Tasks performed in offline mode sync with Procore once a network connection is reestablished. 

Steps

  1. Navigate to the Site Diary tool using the Procore app on an Android mobile device.
  2. Tap the date to select the calendar day for which you want to create a new entry.
  3. Tap icon-plus-quick-create-mobile2.png to create a new entry.
  4. Tap Plan Revisions
  5. Tap into the following fields to enter the relevant information:
    • Revision Title: Tap the Revision Title field. Enter the revision title that appears on the plans.

    • Plan #: Tap the Plan # field. Enter the number that appears on the plan submitted.

    • Revision: Tap the Revision field. Enter the revision number that appears on the plans.

    • Category: Tap the Category field. Enter the category of discipline that appears in the revision.

    • Comments: Enter any comments that may be needed to further describe the entry.

  6. Tap Save.