Skip to main content
Procore

Bulk Edit Projects in Workforce Planning

Objective

To bulk edit project in Workforce Planning.

Background

You can edit projects in Workforce Planning. Sometimes, multiple projects may need the same updates. In these cases, you can bulk edit projects to change details about multiple projects at once.

 Note

Projects can be created in either Procore or Workforce Planning, but your company must choose one as your system of record. Your Procore point of contact guides your company through this decision based on your setup. 

This article is for customers who have Workforce Planning as their system of record for project creation and management.

Things to Consider

Steps

  1. Navigate to the Company level Workforce Planning tool.
  2. Click Projects and select Project List.
  3. Mark the tickboxes of the projects you wish to edit.
  4. Click Batch Actions and select Batch Edit.
    clipboard_e9981d43adae77740ee100f15718ce5da.png
  5. Select the field you want to edit for all the projects you selected:
    • Address. Enter the projects' street address.
    • Address 2. Enter the projects' street address, continued.
    • Tender Rate. Enter the projects' average rate per hour, also referred to as the 'Estimated Average Rate'.
    • City. Enter the projects' city or town.
    • Colour. Select the projects' colour.
    • Country. Enter the projects' country.
    • Customer. Enter the customer for whom the projects are for.
    • End Time. Enter the projects' daily end time.
    • Est. End Date. Enter the projects' estimated end date.
    • Groups. Select the projects' groups.
    • Name. Enter the projects' name.
    • Percent Complete. Enter the percent that the projects are complete.
    • Postal. Enter the projects' postcode.
    • Project #. Enter the projects' project number.
    • Project Type. Enter the type of project.
    • Roles. Select the Job Title and add the Person assigned to that job title for the projects. See Configure Job Titles in Workforce Planning.
    • Start Date. Enter the projects' start date.
    • Start Time. Enter the projects' daily start time.
    • State. Enter the projects' state or province.
    • Status. Enter the projects' 'Status' by selecting Active, Pending or Inactive.
    • Tags. Select the projects' tags. See Configure Tags for Workforce Planning.
    • Timezone. Select the projects' timezone.
  6. Click Save to save.