Objective

To enable the importing of billed rate transactions into Procore for companies using the Procore + Sage 300 CRE® integration.

Background

If your Procore company account is integrated with Sage 300 CRE®, you have the ability to import billed rate transactions from Sage 300 CRE®. This is done by designating specific cost types as billed rate transactions. Transactions with this designation differ from other job cost transactions in that they import the value from the Billed Amount in Sage 300 CRE®. Once imported,  the values of those transactions can be viewed in the 'Direct Costs' column on a budget line item in a Procore project. In addition, users who are assigned the appropriate granular permission can also click the values in the 'Direct Costs' column in the budget tool to open a window showing detailed information about the item.

  • Add a 'Direct Costs' source column to your Procore project's budget view
    Provides authorized users with the ability to add a 'Direct Costs' column to your project's budget view. 
  • Track Sage 300 CRE® direct costs in a Procore budget
    Once the 'Direct Costs' column has been added to a budget view, project users with access permissions to the budget can view the lump-sum totals from the Sage 300 CRE® job cost transactions as a direct cost value on a budget line item. The value in this column shows your project's 'Direct Costs' total for all items in the 'Pending', 'Revise and Resubmit', and 'Approved' status. Note: An accounting approver can sync the job cost transaction details from the Sage 300 CRE® on the Job Costs tab of the ERP Integrations tool.
  • View direct cost transaction detail on a budget line item.
    Project users with the 'View Direct Cost Detail' granular permission enabled on their permission template can click the hyperlink in the Direct Costs column of a budget line item to open the direct cost's details in a popup window. This granular permission is located in the 'Budget' area when configuring a permission template.

Things to Consider

  • Required User Permissions:
    • To enable this setting, 'Admin' on the project's Admin tool. 
    • To submit a request to enable the feature in your company's Procore account, you must be your company's Procore Administrator or the designated ERP Integration Contact on your company's Procore account. 
  •  Supported ERP Integrations:
    This feature is supported in these integrated ERP systems.
    • Sage 300 CRE®
  • Requirements:
    To enable this feature on a Procore project:
    • You must be sending costs to the Billing (BL) module in Sage 300 CRE® and using the Billing module to generate Work in Progress (WIP) to use this feature.
    • Your company's Procore Administrator must contact Support specifying which cost types should be designated as billed rate transactions.
    • A user with administrative privileges to your company's Sage 300 CRE® server must follow the steps in Setup the hh2 Sync Client to Sync Job Cost Transactions.
    • Your Procore Administrator (or a user with 'Admin' permission on the project's Admin tool) must enable the job cost transactions syncing capability as described below.
    • Your Procore Administrator must update your project's budget view(s) to complete these steps:
      1. If you have previously completed the steps described in Add the 'ERP Direct Costs' Column to a Procore Budget View for ERP Integrations, you will need to remove both the existing 'ERP Direct Costs' calculated column and the 'ERP Job to Date Costs' source column. 
      2. After removing these columns, you will need to add the recommended columns for job cost transaction syncing to your budget view. For instructions, see Add the Columns for Job Cost Transaction Syncing to a Budget View for ERP Integrations.

Steps

  1. Navigate to the project's Admin tool. 
  2. Under Project Settings, click General.
  3. Scroll to Advanced Settings.
  4. Place a tick in the Enable ERP Job Cost Transaction Syncing tickbox.
    This action enables the syncing feature in the project.