Skip to main content
Procore

Edit a Main Contract

Objective

To edit a project's main contract

Background

You can edit a main contract at any time before you place it into the 'Approved' status.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's Main Contracts tool.
      OR
    • 'Read Only' or 'Standard' level permissions on the project's Main Contracts tool with 'Update Main Contracts' granular permission enabled on your permissions template.
  • Additional Information:
    • Some fields cannot be edited when items are in the 'Approved' status. For example, you cannot edit a Bill of Quantities (BOQ) on an owner payment application or Main Contract Variation (MCV) is already in the  'Approved' status.

Prerequisites

Steps

Edit a Main Contract

  1. Navigate to the project's Main Contracts tool.
  2. Locate the contract to work with, then click its Number link. 
  3. Click Edit
  4. In the General tab, under General Information, modify the following information as needed:
    Notes: There are no required fields when creating a new main contract. If you click Create without completing any data entry, the system saves the contract with your name listed as the creator and places it in the Draft status by default.
    • Sign with DocuSign©
      If you are using the Procore + DocuSign© integration (see DocuSign©), a tick appears by default. Clear the tick from the box if the main contract does NOT require a DocuSign© signature. 
    • Contract #
      Accept the default contract number, enter a new number for the main contract or create a custom numbering scheme to use.
      Notes
      • If you plan to create multiple main contracts, Procore increments this number for you by default. For example; 1, 2, 3 and so on. 
      • To use a custom numbering scheme, you can enter a set of alphanumeric characters (for example, PC-1 or PC-01 or PC-001) and Procore increments the number on new contracts.
    • Title
      Enter a descriptive name for the main contract.
    • Owner/Client
      Select the project owner/client from the drop-down list.
    • Architect/Engineer
      Select the lead architect for the project from the drop-down list.
    • Contractor
      Enter the company name of the primary contractor managing the construction project. If you are setting up the main contract, this will typically be your company's name. 
    • Status
      Select the current status for the main contract. Options include Draft, Out for Tender, Out for Signature, Approved, Complete or Terminated.
      Note: 
      To create variations and payment applications, a main contract's status must be set to Approved or Complete.
    • Executed
      Place a mark in this check box if the contract has been fully executed.
    • Make this Visible Only to Administrators and the Following Users
      Place a mark in this check box to limit visibility to users with 'Admin' permission and any users designated in the 'Allow These Users to See BOQ Items' checkbox.
    • Allow These Users to See BOQ Items
      Place a mark in this check box. Then select the names of any users who have been granted 'Standard' or 'Read Only' permissions on the Main tool from the 'Select a Person' drop-down list.
    • Default Retention. Specify a default percentage that will automatically be applied to all line item costs for retention purposes.  For example, enter: 10%
    • Description
      Enter a descriptive summary to provide more detail about the main contract.
    • Attachments
      Attach any relevant files to the main contract. For example, an electronic copy of the signed contract.
  5. Under Contract Dates, do the following:
    • Date Created
      Shows the date the contract was created. This cannot be modified.
    • Start Date
      Specify the project's official start date.
    • Estimated Completion Date
      Specify the estimated date for project completion.
    • Substantial Completion Date*
      Select the date from the calendar control. The substantial completion date refers to the date that work is considered sufficiently complete to satisfy contractual requirements. It also indicates the date that the project owner or client can assume occupancy of all or part of a project and the main contractor is entitled to receive contract balance payment (less retention) until final completion.
      Note: If enabled, the substantial completion date will be updated to each Main Contract Variation's Revised Substantial Completion Date once each Main Contract Variation has a status of Approved.
    • Actual Completion Date
      Select the date from the calendar control. This represents that final payments have been processed and the contract is considered closed.
    • Contract Date*
      Select the date from the calendar control. This represents the effective date of the contractual agreement. This is the date the contract goes into force. 
    • Signed Contract Received Date
      Select the date from the calendar control. This represents the date that the executed contract was received. 
       Tip
      Will you be collecting signatures on this contract with DocuSign©If so, be aware that the 'Signed Contract Received Date' field is labelled 'Signature Required' field after a user clicks the Sign with DocuSign© button or if the DocuSign© envelope has been sent to recipients and is awaiting signature(s) (i.e., while awaiting signatures, the status of the contract is set to Pending). When the final signature is completed, the Procore + DocuSign© integration updates this field to show the signature date. You can now click View to open the signed PDF in DocuSign©
    • Execution Date*
      Select the date from the calendar control. This represents the date the agreement was signed by all parties. 
    • Issued On Date*
      Select the date from the calendar control. This date represents the date the contractual agreement was issued to both parties.
    • Returned Date
      Select the date from the calendar control. 
    • Letter of Intent Date
      Select the date from the calendar control. A letter of intent date is the date the Letter of Intent (LOI) document outlining the agreement between parties is received before the contract is finalized. 
    • Approval Letter Date*
      Select the date from the calendar control. A letter of approval date is the date that compliance with the fees, statements and disclosures stated in the Letter of Approval (LOA) for the contract was signed into the record. 
    • Contract Termination Date
      Select the date from the calendar control. A contract termination date is a date outlined in the main where all parties have met all contractual obligations and terms.
  6. Under Additional Information, do the following:
    • Inclusions. Specify any agreed-upon inclusions in the contract.
    • Exclusions. Specify any agreed-upon exclusions in the contract.
  7. Click Save.

Add, Delete and Rearrange BOQ Line Items 

  1. Navigate to the Main Contracts tool.
  2. Click the Bill of Quantities tab.
  3. Click the vertical ellipsis (⋮). Then choose from the following menu options:
    view-prime-contract-sov-options.png
    • Add Above. Select this option to add a line item above the current line item. 
    • Add Below. Select this option to add a line item below the current line item. 
    • Delete. Select this option to delete the current line item. 
       Tip
      To rearrange line items in the list, you can type over the numbers in the # column. This lets you specify the list order of each item on the BOQ. 
  4. Click Save.