Objective
To change the status of a task.
Background
When editing a task, you can change its status. If you have completed the work associated with task and want to close it, choose the Closed status. If you want to close a task without completing it because the work is no longer required, choose the Void status.
Things to Consider
Steps
- Navigate to the project's Tasks tool.
- Locate the task you want to change the status of.
- Click Edit.
- Select a status from the Status list:
- Initiated: Indicates the task has been created.
Note: This is the default status. - In Progress: Indicates work on the task has started.
- Ready for Review: Indicates the task is complete and ready for review.
- Void: Indicates the task has been voided.
- Closed: Indicates the task has been reviewed and the work has been successfully completed.
- Initiated: Indicates the task has been created.
- Click Save.