Skip to main content
Procore

What are Milestone Dependencies in Portfolio Financials and how do I set them?

 Note
This information is intended for accounts with Portfolio Financials product in Procore. Please reach out to your Procore point of contact for more information. 

Answer

Milestone Dependencies allow you to establish a relationship between two milestones so that you can track and maintain project programmes more efficiently. For example, a 'Construction Start' milestone can be dependent on the date for the 'Drawings Complete' milestone. If the forecast date for 'Drawings Complete' is adjusted by 10 days, the forecast date for 'Construction Start' will also adjust by 10 days.

Notes:

  • You cannot set a dependency for the first milestone listed, as nothing precedes it.
  • You can only set a milestone dependency when adding a new milestone manually, as opposed to from a template. 

Steps

To set a dependency for a new milestone:

  1. In the Milestones section of the Project Page, click Add Milestone.
  2. Enter a title and date for the milestone. See Add Milestones to a Project in Portfolio Financials.
  3. Click the Dependencies drop-down menu and select a dependency. 
  4. Click Add

To set a dependency for an existing milestone:

  1. Click the plus blue-plus-pfcp.png icon in the 'Dependencies' column for the milestone you want to set a dependency for.
  2. Select the milestone that you want it to be linked to.

    select-dependencies.png

    Note: If you change the Forecast Date for a milestone, the dependent milestone's Forecast Date will also update.