What are the default 'Scope' options for change events in Procore?

Background

When creating or editing a change event in a Procore project, you can select one of Procore's pre-defined 'Scope' options to classify the scope of the change being considered.

Answer

The table below details the different options in the 'Scope' drop-down list of a change event. 

Status When creating or editing a change event...
In Scope
  • Indicates the cost of the change event is covered within the terms of the original contract. 
Out of Scope
  • Indicates the cost associated with the change event is not covered by the original contract. 
  • When a change event is 'Out of Scope', you will typically create a variation to amend the original contract.
TBD
  • Indicates the cost impact of the change event on the original contract has not yet been determined. 

 

 

If you would like to learn more about Procore's change events management software and how it can help your business, please visit our construction variation product page icon-external-link.png.