What data columns are available in a bill of quantities on an owner payment application ? (Beta - Draft)

 In Beta 

This content is for participants in the Project Financials: Modernised Owner Payment application Experience beta program.

Answer

The data column layout of an owner payment application depends on these factors:

Main Contract Payment Applications: Bill of Quantities Data Columns

When you set the accounting method to use on a main contract's Bill of Quantities, that method is automatically applied to the contract's main contract payment applications. See How do I set the accounting method for a contract? Each accounting method has a unique column layout that includes specific columns and column groups designed specifically to work for each accounting method. For both methods, you can expand and collapse each column group by clicking these icons:

  • expand-column-group.png Expand Column Group. Click to expand the columns in the group. 
  • collapse-column-group.png Collapse Column Group. Click to collapse the columns in the group. 

Amount-Based Accounting Method

When an owner payment application uses the amount-based accounting method, you'll see these columns. 

amount-based-owner-invoice.png

Default Columns

This table details the default columns for main contract payment applications with the amount-based accounting method. An asterisk (*) by a 'Column Name' indicates the column is only visible when the 'Column Group' is expanded. 

Column Group Column Name Data Entry Field Description
  Item Number red-x.png Show the line item number on the payment application's Bill of Quantities. 
Line Item Details Budget Code red-x.png Shows the budget code for the line item.
  Description of Work red-x.png Shows the description for the line item from the corresponding line item on the contract.
  Line Item Type * red-x.png Shows the line item type. 
  Source * red-x.png Shows the link to the line item source. This includes: BOQ or Variation.
Value Main Contract Value* red-x.png Shows the value of the line item from any 'Approved' variations for the contract. 
  Change Value* red-x.png Shows the value of the line item from any 'Approved' variations. 
  Bill of Quantities red-x.png Shows the line item's bill of quantities from the main contract or variation. 

Where the group total shows, the value is the total sum of all the values on its main contract plus all of its variations. 
Work Completed From Previous Application (£) red-x.png Shows the currency amount for all work completed in previous payment applications. 
  From Previous Application (%) * red-x.png Shows the percentage value for all work completed in previous payment applications. 
  This Period green-check.png Enter a currency amount for all work completed this billing period.
  This Period (%) * green-check.png Enter a percentage value for all work completed in this billing period. 
Materials Previous Materials Stored* green-check.png Enter a currency amount that represents the total of all materials stored in previous billing periods. 
  New Materials Stored* green-check.png Enter a currency amount for all materials stored in this billing period.
  Materials Presently Stored red-x.png Shows the currency amount that is the sum of 'Previous Materials Stored' plus 'New Materials Stored.' 
Total Completed & Stored Materials Total to Date (£) red-x.png Shows the currency amount for all completed and stored materials for previous billing periods plus this billing period. 
  Total to Date (%) green-check.png Enter a percentage value for all completed and stored materials for previous billing periods plus this billing period. 
  Balance to Finish red-x.png Shows the remaining currency amount that has yet to be completed and stored for the contract. 
Retention

Note: To fully expand this column group, you may need to collapse other column groups first.
Previous Work Retention * red-x.png Shows the currency amount for any work retention held for work completed from previous billing periods.  
  Previous Materials Retention * red-x.png Shows a currency amount for any materials retention held from previous billing periods. 
  Previous Total Retention * red-x.png Shows the currency amount that is the sum of 'Previous Work Retention' and 'Previous Total Retention.'
  Work Retention This Period (£) * green-check.png Enter a currency amount for the work retention held for this billing period. 
  Work Retention This Period (%) green-check.png Enter a percentage value for the work retention held for this billing period. 
  Total Work Retention * red-x.png Shows a currency amount for the total work retention held for previous billing periods plus this billing period. 
  Materials Retention (£) * green-check.png Enter a currency amount for materials retention held for this billing period. 
  Materials Retention (%) green-check.png Enter a percentage value of materials retention held for this billing period.
  Work Retention Released This Period * green-check.png Enter a currency amount of work retention released for this billing period. 
  Total red-x.png Shows the total retention. Procore calculates this value as:
('Total Work Retention' + 'Materials Retention (£)') - 'Total Retention Released This Period'.

This 'Total' is analogous to the definition of 'Retention' on common industry-standard forms.

Unit/Quantity-Based Accounting Method

When main contract payment applications use the unit/quantity-based accounting method, you'll see these columns. 

unit-quantity-owner-invoice.png

Default Columns

This table details the default columns for main contract payment applications with the unit/quantity-based accounting method. An asterisk (*) under 'Column Name' indicates the column is only visible when the 'Column Group' is expanded. 

Column Group Column Name Data Entry Field Description
  Item Number red-x.png Shows the line item number on the payment application's Bill of Quantities. 
Line Item Details Budget Code red-x.png Shows the budget code for the line item.
  Description of Work red-x.png Shows the description for the line item from the corresponding line item on the contract.
  Line Item Type * red-x.png Shows the line item type. 
  Source * red-x.png Shows the link to the line item source. This includes: BOQ or Variation.
Value Programmed Quantity red-x.png Shows the programmed quantity for the line item. 
  Unit Price red-x.png Shows the unit price for the line item. 
  Main Contract Value * red-x.png Shows the value of the line item from the main contract. 
  Change Value * red-x.png Shows the value of the line item from any 'Approved' variations for the contract. 
  Bill of Quantities red-x.png Shows the line item's bill of quantities from the main contract or variation. 

Where the group total shows, the value is the total sum of all the values on its main contract plus all of its variations. 
Work Completed From Previous Application (Qty) red-x.png Shows the unit quantity for all work completed in previous payment applications. 
  From Previous Application (£) red-x.png Shows the currency amount for all work completed in previous payment applications. 
  From Previous Application (%) * red-x.png Shows the percentage value for all work completed in previous payment applications. 
  This Period (Qty.) green-check.png Shows the quantity for all work completed in this billing period.
  This Period (£) red-x.png Shows the currency amount for all work completed in this billing period.
  This Period (%) * red-x.png Shows the percentage value for all work completed in this billing period.
Total Completed & Stored Materials Total to Date (Qty.) * red-x.png Shows the quantity for all completed and stored materials for previous billing periods plus this billing period. 
  Total to Date (£) * red-x.png Shows the currency amount for all completed and stored materials for previous billing periods plus this billing period. 
  Total to Date (%) * green-check.png Enter a percentage value for all completed and stored materials for previous billing periods plus this billing period. 
  Balance to Finish * red-x.png Shows the remaining currency amount that has yet to be completed and stored for the contract
Retention

Note: To fully expand this column group, you may need to collapse other column groups first.
Previous Work Retention * red-x.png Shows a currency amount for any materials retention held from previous billing periods. 
  Work Retention This Period (£) * green-check.png Enter a currency amount for the work retention held for this billing period. 
  Work Retention This Period (%) * green-check.png Enter a percentage value for the work retention held for this billing period. 
  Work Retention Release This Period * green-check.png Enter a currency amount for the work retention released for this billing period. 
  Total red-x.png Shows the total retention. Procore calculates this value as:
('Total Work Retention' + 'Materials Retention (£)') - 'Total Retention Released This Period'.

This 'Total' is analogous to the definition of 'Retention' on common industry-standard forms.