What is the difference between the Variations Tool and the Variations Subtab within the Main Contracts and Commitments Tools?
Background
There is a tool at the Project level titled Variations.
Within the Main Contracts and Commitments tools, there are subtabs titled "Variations".
This FAQ outlines the difference between the Variations tool and variation subtabs.
Answer
The variations subtab is located within the Main Contracts and Commitments tools. Within the Main Contracts or Commitments tools, you can manage Potential Variations, Variation Requests and Main Contract or Commitment Variations.
The project's Variations tool is designed as a collaboration area with your client and contractors on Main Contract and Commitment Variations, but will not show a list of Variation Requests and Potential Variations.