Skip to main content
Procore

Add Quantities to a Timesheet (iOS)

Also available on  android-gray-icon.jpg  web-gray-icon.jpg

Objective

To add quantities to a timesheet using the Procore app on an iOS mobile device.

Background

Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures or linear feet of piping. In Procore, there are two types of production quantities:

  • Budgeted production quantities refers to the measurable amount a team plans to install on a project.
  • Installed production quantities refers to the actual amount installed on a project by a point in time.

Use the steps below to enter installed production quantities on a timesheet. One entered, they can then be tracked against the imported budgeted production quantities using the Production Quantity Report.

Things to Consider

Steps            

Now that you have filled in your timesheet, perform the following actions before you submit:

  1. Tap Submit.
  2. Tap Submit and Add Quantities.

    2018-07-10_10-21-27.png
     Notes
    • You will receive an error message if quantities have not been uploaded to the project. See Import a Unit Quantity Based Budget.
    • If the Sub Jobs feature is enabled on your project (see Enable Sub Jobs), the 'Sub Job' associated with your 'Units Installed' entry will appear in the Quantities list.
    • If Sub Jobs is disabled, the 'Sub Job' field will display the word 'None.'
  3. Tap the Quantities field and enter the desired amount.
    Note: The data entered in the Budgeted Quantity import will pull in the Unit Of Measure and Percent Complete based on the cost code.
  4. Click Submit.