Objective
To export a Main Contract Variation (MCV) to your ERP system.
Things to Consider
- Required User Permissions:
- 'Standard' or 'Admin' on the company's ERP Integrations tool.
AND
- The person's account must be granted the 'Can Push to Accounting' privilege in the Company Directory. See Grant Accounting Approver Privileges.
- Prerequisites:
- The Main Contracts and Variations tools must be enabled on the project(s) that you want to sync.
- Requirements:
- There must be a Main Contract synced between the Procore Project and your ERP system.
- The 'Date Created' field on the MCV is required.
- The MCV must be in the 'Approved' status.
- Not all ERP integrations support the sync of MCVs or main contracts. Additional requirements, considerations and limitations will vary depending on the ERP system your company is integrated with. See Things to Know about your ERP Integration for details.