Create a Funding Variation from a Change Event
Objective
To create a Funding Variation from a change event.
Background
If the Change Events tool is enabled on your project, your project's variation tier configuration setting (see What are the different variation tier settings in Project Financials?) determines the number of steps leading up to creating a funding variation.
- If the 1-tier variation setting is enabled, you will simply use the steps below to create a funding variation from a change event.
- If the 2-tier variation setting is enabled, you will complete the first step in the change management process, Create a Potential Variation for a Funding, before using the steps below.
- If the 3-tier variation setting is enabled, you will complete the first two steps in the change management process, Create a Potential Variation for a Funding and Create a Variation Request, before using the steps below.
Tips
Are you inviting your downstream collaborators to submit tenders for goods and services using formal RFQs?
If your project team has opted to use Procore's Request for Quote (RFQ) process (see Create RFQs from a Change Event), you do NOT have to wait until the RFQ process is complete to create your funding variation. However, after invited collaborators respond to RFQs and its status is set to 'Pending Final Approval,' Procore does automatically update the variation's Bill of Quantities (BOQ) with the appropriate amounts from the RFQ.
To learn more about how the RFQ process affects funding variations, see What are the different RFQ statuses and how do they affect cost and variation amounts?
Are you using the Revenue ROM function?
If your project team has opted to use the Revenue ROM function, the BOQ on your funding variation is also automatically updated. If you have hidden the Revenue ROM function, any automatic updates depend upon the scope of the change event:
- When change events are 'In Scope' or 'TBD', the variation's bill of quantities is automatically updated with a £0 value.
- When change events are 'Out of Scope', the variation's bill of quantities is automatically updated using the data in the RFQ. This update occurs when the RFQ status is set to 'Pending Final Approval.'
- When change events are not in one of the above statuses, the variation's bill of quantities is automatically updated using the 'Cost ROM'.
Things to Consider
- Required User Permissions:
- 'Standard' or 'Admin' level permissions on the project's Change Events tool.
AND - 'Standard' or 'Admin' level permissions on the project's Funding tool.
Notes
For users with 'Standard' level permissions on the project's Funding tool to perform this task, the following must also be true:- The user must be added to the 'Private' drop-down list of the main contract. See Create Fundings.
- If the project is configured to use the two (2) or three (3) tier variation setting (see What are the different variation tier settings in Project Financials?), the 'Allow Standard Users to Create PV's' tickbox setting must be enabled. See Configure Settings: Funding.
- 'Standard' or 'Admin' level permissions on the project's Change Events tool.
- Required Configuration Setting:
- To complete the steps below, you must enable the 1-tier configuration setting for Client Contract Variations. See Configure the Number of Funding Variation Tiers.
- Additional Information:
- After you create a change event, you can also create an RFQ to send to the affected collaborator(s). See Create RFQs.'
- If your company has enabled the ERP Integrations tool, keep these items in mind:
- QuickBooks® Desktop:
- Funding variation exports are NOT supported.
- Sage 100 Contractor®:
- Funding variation exports are NOT supported.
- Sage 300 CRE®:
- Title. The variation title must be 30 characters or less.
- Number (#). The variation number be five (5) characters or less.
- Status. The funding must be in the Approved status.
- Associated Line Item. For each line item that you add to the variation's Bill of Quantities (BOQ), you may designate one (1) associated line item for each variation line item or the same associated line item for all variation line items. Note: The Associated Line Item list is only visible and available when the ERP Integrations tool has been configured to work with Sage 300 CRE® and the export main contract variations capability has been switched on in Procore by your Integration Implementation Specialist.
- Integration by Procore:
- Funding variation exports are NOT supported.
- Viewpoint® Vista™:
- Funding variation exports are supported.
- QuickBooks® Desktop:
Prerequisites
- The Change Events tool must be enabled on the project. See Add and Remove Tools on a Project.
- Your project's Funding must be in the 'Approved' status. See Approve a Funding.
Steps
- Navigate to the project's Change Events tool.
- Select one or more change event line items to include in the new variation.
Note
Procore uses the selected line items to populate the variation's bill of quantities. - From the Bulk Actions drop-down menu:
- For one (1) tier variations, choose Create Funding VAR.
OR - For two (2) or three (3) tier variations, choose Create Funding PV.
- For one (1) tier variations, choose Create Funding VAR.
- Complete the following:
- Click Create. Procore creates the variation.