2020
Below are the notable changes to the project's Snag List tool in 2020.
Working Days for Due Dates on Snag List Items (9/3/2020)
With the newly added ability to configure which days are classified as 'working days' in a project, due dates for snag list items will now depend on the project's 'working days'. See Set Project Working Days and Configure Advanced Settings: Snag List.
Updates to Snag List Item PDF Export (4/3/2020)
Additional fields from a snag list item are now included in a PDF export of the snag list item. See Export a Snag List Item as a PDF.
Create Custom Fields for Snag List Tool (19/2/2020)
Company Admin users can now create custom fields and add them to configurable fieldsets in the Snag List tool. See Create New Custom Fields.