Update and Upload a Project Programme File
Objective
To update the project programme in the native software and upload the programme updates into Procore.
Things to Consider
PROCORE SUPPORT: INTERNAL NOTES
If a customer using Primavera P6 asks about percent complete:
P6 has an attribute on activities called Percent Complete Type. This specifies which one of the three percent complete values (Duration, Physical and Units) should be reported. Procore reads this setting and returns the specified percent complete type to Procore.
Steps
- Navigate to the project's Programme tool.
- From the Gantt view, click + Upload Programme.
Note: You are automatically redirected to the Update Programme page in the tool's Configure Settings. - Select a programme file from your computer.
- Click the Attach File link and select your programme file.
OR - Drag the programme file from your computer to the Drag and Drop File area.
- Click the Attach File link and select your programme file.
- Navigate to the programme file on your computer or network, then click Open.
- Scroll to the bottom of the page and click Update.
Note:- A "Programme Uploaded, processing should start soon" message appears. Your programme is placed into a job queue and the system updates the programme on a task-by-task basis. Depending on the number of jobs in the queue and the size of your project programme, the overwrite process may take some time to complete. You can continue working in Procore during this process
- Important! While the programme is being updated, it is recommended that you do not attempt to upload another programme update. Doing so will add a second job to the queue and jobs will be processed in the order they were uploaded into the system.