Create a Main PV from a Change Event
Objective
To create a potential variation for a main contract from a change event.
Background
If your company has configured your project to use a two (2) tier variation structure, the change event process requires you to create a potential variation. Then, you will create the MCV from the Main Contract tool. When you create a PV, the Bill of Quantities (BOQ) will populate with the Latest Price values.
Things to Consider
- Required User Permissions:
- 'Standard' level permissions or higher on the project's Change Events tool.
AND - 'Standard' level permissions on the project's Main Contracts tool and the 'Allow Standard Level Users to Create PVs' configuration setting must be enabled on the Main Contracts tool. See Configure Settings: Main Contracts.
- 'Standard' level permissions or higher on the project's Change Events tool.
- Additional Information:
- Depending on the variation tier configuration setting configured for the Main Contracts tool, potential variations can be transitioned into one (1) of the following items:
- For two (2) tier variations, a main contract variation.
- For three (3) tier variations, a variation request.
- To learn more see, What are the different variation tier settings in Project Financials?
- Depending on the variation tier configuration setting configured for the Main Contracts tool, potential variations can be transitioned into one (1) of the following items:
Prerequisites
- The Change Events tool must be turned ON on the project. See Add and Remove Project Tools.
- The two (2) tier variation configuration settings must be turned ON the Main Contracts tool. See Configure the Number of Main Contract Variation Tiers.
- The project's main contract must be in the 'Approved' status. See Approve a Main Contract.
Steps
- Navigate to the project's Change Events tool.
- In the table, mark the tickboxes for one (1) or more change event line item(s) to include in the new potential variation.
Note
Procore creates the potential variation's Bill of Quantities (BOQ) using the selected change event line item(s). - Click the Bulk Actions menu and choose the Create Main PV option. Then choose the appropriate contract option from the sub menu.
- In the 'New Potential Variation' page, complete the following data entry:
-
Note
If the Request for Quote (RFQ) feature is turned ON, you can configure the Change Events tool to include any attachments added to a reviewer's RFQ response. For instructions, see Configure Settings: Change Events.
- Click Create.
Notes
- The Associated Line Item drop-down list only appears if your company's Procore account is integrated with an integrated ERP system and the Main Contracts tool is active on the project.
- When adding line items to the variation's bill of quantities, you must select an Associated Line Item for each new line item. You can designate one (1) associated line item or use the same associated line item for multiple line items. Choosing to create a new line item to associate will automatically create a new zero (0) monetary line item on the contract's original BOQ.