(Beta) Create Funding Variations
Objective
To create a Funding Variation (FV).
Background
Use the steps below when you want to create a variation for a funding.
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Funding tool.
- Additional Information:
- If the Change Events tool is active in Project Tools, you must complete the steps in Create a Change Event before the steps below.
- For companies using the ERP Integrations tool: Show/Hide
- Not all ERP integrations support the sync of variations. For those that do, additional requirements, limitations and considerations vary depending on the ERP system your company's account is integrated with. See Things to Know About your ERP Integration for details.
Prerequisites
Steps
- Navigate to the project's Funding tool.
- Locate the funding to work with. Then click its Number link.
- Click Create and choose the Create Funding VAR option.
- Complete the following fields:
- Sign with DocuSign©
If the Procore + DocuSign© integration is enabled, a tick appears by default. Clear the tick from the box if you do NOT want to collect signatures with DocuSign©.Tip
How do you collect signatures with DocuSign? After the data entry for the subcontract is complete, change its status to 'Approved' and click the Complete with DocuSign button. This launches the DocuSign® application. If you have not previously signed in, you will be prompted to Sign In to DocuSign®. After you are signed in, you can proceed with Prepare a DocuSign® Envelope for Signature. - Variation #
Accept the default contract number, enter a new number for this contract or create a custom numbering scheme for this contract and future contracts.Notes
- If you plan to create multiple variations, Procore automatically assigns new numbers in sequential order. For example; 001, 002, 003 and so on.
- To use a custom numbering scheme, enter any set of alphanumeric characters and Procore automatically assigns new numbers in sequential order using your custom scheme. For example, enter FV-1, FV-01 or FV-001.
- Date Created
Shows the date and time the funding variation was created. You cannot change this date. - Revision
Displays the funding variation's revision number. When a funding variation is first created, its revision number is zero (0). A funding variation could have multiple revisions because of feedback from a reviewer/approver. - Created By
Displays the name of the user that created the funding variation. You cannot change this name. - Title
Enter a title for the funding variation. - Status
Select the current status of the funding variation. To learn more, see What are the default statuses for variations in Procore? - Private
Mark this tickbox if you want to make the funding variation 'Private' and visible only to users with 'Admin' on the Funding tool. - Due Date
Select a due date for when the funding variation must be approved by. - Issued Date
Select the date when the funding variation was issued. - Designated Reviewer
Select the Procore project user at your organisation who will be responsible for approving or rejecting this funding variation later.Important
- The 'Designated Reviewer' can submit an approve or reject response when a variation is in these statuses:
- Pending - In Review
- Pending - Revised
- To send an email notification to the 'Designated Reviewer' to notify that person that a variation is awaiting their response, you have these options:
- You can forward the funding variation to the 'Designated Reviewer' by email. See Forward a Variation to a Project User by Email.
- The pending funding variation will also be listed in the 'My Open Items' area in the Project Home page.
- After the 'Designated Reviewer' submits an approve or reject response, the 'Reviewer' field (directly below the 'Designated Reviewer' field) shows the date/time stamp of that person's response. The 'Reviewer' field is only visible to the 'Designated Reviewer.'
- The 'Designated Reviewer' can submit an approve or reject response when a variation is in these statuses:
- Paid Date
Select the date that payment was received for the funding variation. - Description
Enter a more detailed description of the funding variation. - Programme Impact
If this funding variation is expected to impact the construction project's programme, enter the estimated number of additional days this would add to the programme. - Revised Substantial Completion Date
Enter an updated substantial completion date for the project.Note
If the substantial completion date is enabled on the Funding tool, Procore updates the funding variation's 'Revised Substantial Completion Date' field after the funding variation is placed into the Approved status. See Configure Settings: Funding. - Executed
Mark this tickbox after the funding variation is fully executed. - Variation Requests
If the Funding tool is configured for three (3)-tier variations, select any variations related to this funding variation from this drop-down list. See Configure the Number of Variation Tiers for the Funding Tool. - Potential Variations
If the Funding tool is configured for two (2)-tier variations, select any potential variations related to this funding variation from this drop-down list. See Configure the Number of Variation Tiers for the Funding Tool.
- Sign with DocuSign©
- Choose one (1) of these options:
- To create the funding variation, click Create.
OR - To create the funding variation and send email notifications, click Create & Email.
- To create the funding variation, click Create.