Skip to main content
Procore

Delete Budgeted Labour Hours and Budgeted Production Quantities

Objective

To delete budgeted labour hours and budgeted production quantities from the Unit Quantity Based Budget page.

Background

If you want to delete budgeted labour hours and budgeted production quantities from the Unit Quantity Based Budget page, the steps you use will depend upon whether the project's Budget tool is enabled.  

Things to Consider

Prerequisites

  • If the Budget tool is enabled, users will need to first delete labour hours from the budget by deleting its corresponding budget line items. See Delete a Budget Line Item for more information.

Steps

If Budget Tool is Disabled

  1. Navigate to the project's Admin tool.
  2. Under "Project Settings", click Unit Quantity Based Budget.
    unit quantity based budget button.jpg
  3. Locate the line item of budgeted labour hours and production quantities you want to delete.
  4. Hover to the far right of the line item to display the rubbish bin icon-delete-trash.png icon.
    delete-timesheet-quantities-from-admin.png
  5. Click the rubbish bin icon-delete-trash.png icon.
  6. Click Delete Labour Hours, Delete Production Quantities, or Delete Both in the “Delete Labour Hours and Production Quantities ” window.

If Budget Tool is Enabled

Note: You can only update or delete Labour Hours from the Budget tool. See Delete a Budget Line Item.

  1. Navigate to the project's Admin tool.
  2. Under 'Project Settings,' click Unit Quantity Based Budget.

    unit quantity based budget button.jpg
     
  3. Locate the line item of budgeted labour hours and production quantities you want to delete.
  4. Hover to the far right of the line item to display the rubbish bin icon-delete-trash.png icon.

    delete-timesheet-quantities-from-admin.png
     
  5. Click the rubbish bin icon-delete-trash.png icon.
  6. Click Delete Production Quantities in the “Delete Labour Hours and Production Quantities ” window.