Overview

To define your organisation's Work Breakdown Structure (WBS) for your company's Procore  account. 

Background

This guide shows your company's Procore Administrator how to set up and define a WBS for use with the projects in your company's Procore account. 

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the company's Admin tool. 

Workflow

If you are your company's Procore Administrator, click the steps in the workflow diagram to jump to the tutorials about creating your company's WBS. 


START
START
Do you want to customize Procore's default company level WBS?
Do you want to customize Procore's default com...
Do you want to edit or delete any segment items before proceeding?
Do you want to edit or delete any segm...


Add Segments to the Company Budget Code Structure
Add Segments to the Company...


Import Segment Items with Procore Imports 2
Import Segment Items...


Add Custom Segments
Add Custom Segments


Add Segment Items
Add Segment Items
Choose from these options
Choose from these options


Edit Segment Items
Edit Segment Items


Edit Custom Segment Settings
Edit Custom Segment S...


Delete Custom Segments
Delete Custom Segments
Choose from these options
Choose from these options
Do you want to add custom segment items to the default segments?
Do you want to add custom segment items...
Do you want to verify your cost code/cost type settings?
Do you want to verify your cost code/cost...


View Company Cost Code Segment Settings
View Company Cost Cod...


View Company Cost Type Segment Settings
View Company Cost Typ...
Choose from these options
Choose from these options


END
END


END
END
Do you want to add custom segments to your company level WBS?
Do you want to add custom segments to your com...
LEGEND
LEGEND
Procore Administrator
Procore Administrator
'Admin' on Project Admin
'Admin' on Project Admin
1
1
You cannot remove the default segments 'Cost Code' and 'Cost Type'. These default segments are required.
You cannot remove the default segments...
Procore Imports
Procore Imports
Company Admin Tool
Company Admin Tool
Do you want to change the segment order of your company budget code structure?
Do you want to change the segment order of your comp...


Arrange the Company Budget Code Structure
Arrange the Company B...
Cost Codes
Cost Codes
Cost Types
Cost Types
Do you want to customize your cost codes and/or cost types?
Do you want to customize your cost codes a...


Add Company Cost Codes
Add Company Cost Code...


Import Segment Items with Procore Imports 2
Import Segment Items...
Choose one of these options
Choose one of these options
Continue to the 'Create Your Project's Work Breakdown Structure' workflow
Continue to the 'Create Your P...
Continue to the 'Create Your Project's Work Breakdown Structure' workflow
Continue to the 'Create Your P...
2
2
In WBS, cost codes and cost types are imported as segment items in Procore's default 'Cost Code' and 'Cost Type' segment.
In WBS, cost codes and cost types are impor...


Import Segment Items with Procore Imports 2
Import Segment Items...
Choose one of these options
Choose one of these options


Add Company Cost Types
Add Company Cost Type...