Create a Variation Request for a Commitment
Objective
To create a variation request for a purchase order or subcontract.
Background
If your project is using the three (3) tier variation setting, a variation request gives contractors the ability to package one (1) or more potential variations into a formal request that you can send out for approval. When creating a variation request, it is a common practice to group commitment potential variations that share the same scope of work into a variation request. This helps to organise your variations into logical groups, which can streamline the review and approval process.
Important
In Procore, variation requests are only created when your project's Commitments tool is using the three (3) tier variation setting. The 1- and 2- tier variation settings do NOT use the variation request step. See What are the different variation tier settings in Project Financials?Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Commitments tool.
Prerequisites
- Create a Purchase Order or Create a Subcontract
- The contract must be in the 'Approved' state.
Steps
- Navigate to the project's Commitments tool.
- Click Create VAR Request.
Important
The 'Create VAR Request' button is only available if your project's commitment is in the 'Approved' status.

- Complete the following:
- Number
Accept the default number, enter a new number or create a custom numbering scheme.Tip
How are numbers assigned? To learn how Procore assigns numbers and to understand your custom numbering options, see Can I customise the numbering system for financial objects in Procore? - Date Created
Displays the date and time that the variation request was created. You cannot change this value. - Revision
This field displays the variation request's revision number. When a variation request is first created, its revision number is zero (0). Depending on the feedback you receive from the reviewer/approver, a variation request may have multiple revisions. - Created By
Displays the name of the user who created the variation request. You cannot change this name. - Title
Enter a title that describes the variation request. - Status
Choose as status for the variation request. To learn more, see What are the default statuses for variations in Procore? - Optional: Commitment Variation
Add a variation request to a commitment variation. You can select an existing commitment variation from the drop-down menu or you can create a new commitment variation and the variation request will be added automatically. - Private
Mark this tickbox if you want the variation request to private. A private variation request is visible only to users with 'Admin' permissions on the Commitments tool who have been added to the commitment contract's privacy list. - Description
Enter a more detailed description of the variation request. - Programme Impact
If known, enter an approximate number of additional days that the proposed change would add to the project's current programme. - Potential Variation
Select which potential variation(s) to include in the variation request. - Attachments
Select and attach any relevant documents.
- Number
- Choose from these options:
- To create the variation request, click Create.
OR - To create the variation request and then forward it to recipients, click Create & Email. This takes you to a page where you can select recipients for the email.
- To create the variation request, click Create.

