Create Delay Entries
Background
The delay section allows you to track any delay that occur or exist during the day.
Things to Consider
-
Required User Permissions:
-
To create entries:
-
'Standard' or 'Admin' level permissions on the project's Site Diary tool.
-
-
To create pending entries as a collaborator:
-
'Read Only' or 'Standard' permissions to the Site Diary tool with the 'Collaborator entry only' granular permission enabled on your permissions template.
-
-
-
Additional Information:
-
The delay section must be enabled for the project.
-
You can add custom delay types for the project, as well as disable or enable types.
-
There is no limit to the number of delays you can create for a day. However, if you want to enter a delay that lasts over 24 hours, you will need to enter it on each day it impacts.
-
Users with 'admin' permission to the project's Directory tool can enable delay email notifications for other users.
-
Delays in the Site Diary can be reported on in the Project and Company level Reports tools.
-
If you want to enter weather delay, you can also use the Observed weather conditions section.
-
Steps
-
Navigate to the project's Site Diary tool.
-
Scroll to the delay section.
You can also use the left navigation menu to quickly navigate to the delay section. -
To create an entry, add information to the fields.
Note: Click the caret icon > to expand and v to collapse the field names and their descriptions below.
-
Click Create.
The diary entry is created or added.