Skip to main content
Procore

Respond to a Snag List Item

Objective

To respond to a snag list item.

Background

In Procore, when a punch list item's Ball in Court has shifted to you, a yellow banner appears in the item's details to notify you that your response is needed with selectable response options based on your role. However, 'Admin' level users or users with the 'Respond to Punch Items Assigned to Users within the Same Company' granular permission enabled on their permission template can also respond to the punch list.

Things to Consider

Steps

  1. Navigate to the project's Snag List tool.
  2. Click View next to the item you want to respond to.
  3. Under the yellow banner, select the appropriate response.
    Note: The response options will vary based on your role within the Punch List workflow.
    respond-to-punch-list-item.png
  4. Optional: Include any additional comments in the text box and click Attach File(s) to add any files or photos.
  5. Click Submit.