Enable or Disable the Subcontractor BOQ Tab on the Commitments Tool

Objective

To enable (or disable) the Subcontractor BOQ tab on the Commitments tool. 

Background

In Procore's Commitments tool, the Subcontractor Bill of Quantities (Subcontractor BOQ) tab provides contractors who perform project work with a place to enter a detailed BOQ breakdown about a commitment. The Subcontractor BOQ is separate from a the general BOQ tab on a commitment. Once completed,  the line items on the Subcontractor BOQ can be submitted for review and approval of the work.  By default, the Subcontractor BOQ tab is enabled in Procore's Commitments tool.

There are two ways to enable the Subcontractor BOQ tab:

  • You can enable the tab for all commitments. To do this,  you will need 'Admin' permission on the Commitments tool.
  • You can enable the tab on individual commitments. To do this in the Invoicing tool, you will need 'Standard' permission on the Commitments tool. See Enable of Disable the Subcontractor BOQ Tab on a Commitment.

Once enabled,  the data entered by users on the Subcontractor BOQ tab is automatically included in subcontractor payment applications. To learn more, see About Subcontractor Payment Applications.

Things to Consider

Steps

  1. Navigate to the project's Commitments tool.
  2. Click Configure Settings .
  3. On the Contract Configuration page, scroll to the Default Contract Settings area. 
  4. Mark the Enable Subcontractor BOQ by Default checkbox. 
    Notes:
  5. Click Update.