Skip to main content
Procore

Update a Subcontractor Bill of Quantities as a Payment Application Contact from the Commitments Tool (Legacy)

 Legacy Content

This tutorial details Procore's legacy experience for updating a bill of quantities on a subcontractor payment application as a payment application contact. The information on this page will be replaced with updated content when the modernised subcontractor payment application experience is generally available.

Important! If you are using the beta experience for subcontractor payment applications, please see Update a Subcontractor Bill of Quantities as a Payment Application Contact from the Payment Applications Tool instead of the page below.

Objective

To update a Subcontractor Bill of Quantities on a commitment contract as an payment application contact from the Commitments tool.

Background

If you are a payment application contact who has been invited to provide a detailed breakdown of your bill of quantities on a commitment, you will receive an email message from Procore with the subject line: "[Procore User Name] invites you to break down your Bill of Quantities for this commitment." A Subcontractor Bill of Quantities (Subcontractor BOQ) provides downstream contractors with a way to provide a detailed breakdown of specific line items on the contract's general bill of quantities. 

Example

Let's assume the general 'Bill of Quantities' on a subcontract includes a line item for £8500.00 and the upstream party on the contract has invited you, the payment application contact, to provide a more detailed breakdown⁠—to show in more detail how you are allocating that £8500.00. Below is an example of a completed 'Subcontractor BOQ'. In this example, the payment application contact has successfully added five (5) separate line items to 'Subcontractor BOQ'. You know that you have successfully updated the 'Subcontractor BOQ' when the sum of your new line items equals £8500.00 and the value in the 'Remaining to Allocate' field is £0.00. 

sub-sov-remaining-to-allocate.png

Things to Consider

  • Required User Permissions:
    • To update line items on a Subcontractor Bill of Quantities as a downstream collaborator, you must be designated as an 'Invoice Contact.' See Add Payment application Contacts to a Purchase Order or Subcontract. You must also have:
      • 'Read Only' level permissions on the project's Commitments tool and be a member of the 'Private' list on the General tab of the commitment.
        OR
      • 'Standard' level permissions on the project's Commitments tool. 
  • Additional Information:
    • The Subcontractor Bill of Quantities must be in 'Draft' or 'Revise & Resubmit' status. 
    • The Subcontractor Bill of Quantities must be 'Approved' before users can create subcontractor payment applications against the commitment. 
  • For companies using the icon-erp-synced2.png ERP Integrations tool: Show/Hide  

Steps

Open the Subcontractor Bill of Quantities from the Commitments Tool

 Tip

Did you receive an email inviting you to provide a breakdown of your bill of quantities on a commitment? If you are a payment application contact for the 'Contract Company' on a commitment contract, the company that you are performing work for may invite you to provide a detailed breakdown of the bill of quantities on a commitment contract. To respond to that email instead of using the steps below, see How do I submit a Subcontractor Bill of Quantities for a Procore commitment?

  1. Navigate to the project's Commitments tool.
  2. Click the Contracts tab.
  3. Locate the purchase order or subcontract to work with and click the Number link.
  4. Click the Subcontractor BOQ tab.
  5. Continue with the next step.

Update the Subcontractor Bill of Quantities

If you are a payment application administrator (or a payment application contact who has been invited to update a Subcontractor BOQ), you can perform these steps on the commitment contract.

  1. In the commitment, click the Subcontractor BOQ tab.
     Note
    If you do NOT see a 'Subcontractor BOQ' tab on the commitment contract, a user with 'Admin' level permissions on the Commitments tool must enable it. See Add a Subcontractor BOQ to a Commitment and Enable or Disable the Subcontractor BOQ Tab on the Commitments Tool.
  2. Click Edit
  3. Enter a detailed line-item breakdown in the Subcontractor BOQ tab as follows:
    sub-sov-remaining-to-allocate.png
    • Click the +Add Line Item link.
    • In the Description box add a detailed description of the work to complete. 
    • In the Amount box, add the specific amount for that work. 
    • Continue this step until the 'Remaining to Allocate' amount for that budget code and description reads £0.00.
  4. When you have allocated all of the amounts in the Subcontractor BOQ tab, click the Submit button. 
     Notes
    • The Submit button is dimmed and unavailable until the Remaining to Allocate fields in the Subcontractor BOQ all read £0.00.
    • After you click the button, Procore changes the status of the Subcontractor BOQ to Under Review
    • You will NOT be able to edit your submission unless the payment application administrator changes the status of the Subcontractor BOQ to Revise & Resubmit