For Procore Customers in the United States
When your company applies the 'Owners English' or 'Speciality Contractors English' point-of-view dictionary, you'll see different tool names and term changes in the user interface. Learn how to apply the dictionary options.
- To learn the differences: Show/Hide
-
This table shows the differences in tool names (bold) and terms across the point-of-view dictionaries for Project Financials. These dictionaries are available in US English only. The default dictionary is designed for main contractors, which means that you will need to work with your Procore Administrator at your company and your Procore point of contact to access the other dictionary options.
Main Contractors
English (United States) - Default
|
Owners
English (Owner Terminology V2)
|
Speciality Contractors
English (Speciality Contractor Terminology)
|
Payment Applications |
Payment Applications |
Progress Billings |
Owner |
Funding |
Owner |
Owner/Client |
Owner/Client |
MC/Client |
Main Contract Variation |
Funding Variation |
Client Contract Variation |
Main Contracts |
Funding |
Client Contracts |
Revenue |
Funding |
Revenue |
Subcontract |
Contract |
Subcontract |
Subcontractor |
Contractor |
Subcontractor |
Subcontractor Bill of Quantities (SBOQ) |
Contractor Bill of Quantities (CBOQ) |
Subcontractor Bill of Quantities (SBOQ) |
Objective
How to edit the Subcontractor Bill of Quantities on a commitment as a payment application contact from the Payment applications tool.
Background
If you are a payment application contact who has been invited to provide a detailed breakdown of your bill of quantities on a commitment, you will receive an email message from Procore with the subject line: "[Procore User Name] invites you to break down your Bill of Quantities for this commitment." A Subcontractor Bill of Quantities (Subcontractor BOQ) provides downstream contractors with a way to provide a detailed breakdown of specific line items on the contract's general bill of quantities.
Example
Let's assume the general 'Bill of Quantities' on a subcontract includes a line item for £8500.00 and the upstream party on the contract has invited you, the payment application contact, to provide a more detailed breakdown—to show in more detail how you are allocating that £8500.00. Below is an example of a completed 'Subcontractor BOQ'. In this example, the payment application contact has successfully added five (5) separate line items to 'Subcontractor BOQ'. You know that you have successfully updated the 'Subcontractor BOQ' when the sum of your new line items equals £8500.00 and the value in the 'Remaining to Allocate' field is £0.00.
Things to Consider
- Required User Permissions:
- Additional Information:
- The Subcontractor Bill of Quantities must be in 'Draft' or 'Revise & Resubmit' status.
- The Subcontractor Bill of Quantities must be 'Approved' before users can create subcontractor payment applications against the commitment.
- For companies using the ERP Integrations tool: Show/Hide
- The Subcontractor BOQ in Procore detailed below does NOT sync with the integrated ERP system.
- Only the general BOQ on the commitment in Procore is synced with the integrated ERP system. See Add a Line Item to a Commitment's Bill of Quantities.
Steps
- Navigate to the Subcontractor Bill of Quantities from the Payment Applications Tool
- Update the Subcontractor Bill of Quantities
Navigate to the Subcontractor Bill of Quantities from the Payment Applications Tool
Tip
Did you receive an email inviting you to provide a breakdown of your bill of quantities on a commitment? If you are a payment application contact for the 'Contract Company' on a commitment contract, the company that you are performing work for may invite you to provide a detailed breakdown of the bill of quantities on a commitment contract. To respond to that email instead of using the steps below, see How do I submit a Subcontractor Bill of Quantities for a Procore commitment?
- Navigate to the project's Payment applications tool.
- Click the Subcontractor tab.
- In the table, locate the payment application associated with the commitment.
- Click its Contract link to open it.
Update the Subcontractor Bill of Quantities
If you are a payment application administrator (or a payment application contact who has been invited to update a Subcontractor BOQ), you can perform these steps on the commitment.
- Click the Subcontractor BOQ tab.
- Click Edit.
- Enter a detailed line-item breakdown in the Subcontractor BOQ tab as follows:
- Click the +Add Line Item link.
- In the Description box add a detailed description of the work to complete.
- In the Amount box, add the specific amount for that work.
- Continue this step until the 'Remaining to Allocate' amount for that budget code and description reads £0.00.
- When you have allocated all of the amounts in the Subcontractor BOQ tab, click the Submit button.
Notes
- The Submit button is dimmed and unavailable until the Remaining to Allocate fields in the Subcontractor BOQ all read £0.00.
- After you click the button, Procore changes the status of the Subcontractor BOQ to Under Review.
- You will NOT be able to edit your submission unless the payment application administrator changes the status of the Subcontractor BOQ to Revise & Resubmit.